FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
4 Hardware Installation Preparations
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
47
When heating the screw threads, avoid burning the component and labels around.
Figure 4-30
Removing a plug and installing a conversion adapter
Routing pipes from the bottom is used as an example in
, and it is the same as routing pipes
from the top.
Step 3
Install the side panels.
----End
4.2.4 Removing Transportation Fasteners for the Air Conditioner
Context
This step applies to the model with 1100 mm depth or 1200 mm depth, and electric heater or
water pump.