FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
A Appendix
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
214
(7) Telescopic edges
A.5.5.1 Installing the Skylight Connective Plate
Prerequisites
The sealing plates near the aisle have been installed and secured.
Procedure
Step 1
Secure skylight connective plates to sealing plates or cabinets using eight M8 bolts.
Figure A-16
Installing a skylight connective plate
(1) Column
----End
A.5.5.2 Installing the Telescopic Edges
Procedure
Step 1
Extend the two telescopic edges to an appropriate length and secure them using two M6
screws.