FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
149
Figure 9-53
Securing the pad mounting kit
Step 4
Insert the pad power adapter into the power connector. Bind the access monitoring cable at
the bottom of the power connector holder. Route the access monitoring cable along the outer
side of the power connector holder and route the cable out through the cable hole in the door
box, as shown in
Skip this step if no pad is installed. Route the access monitoring cable from the cable hole in the door
box baffle plate, as shown in