FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
9 Installing Monitoring Devices
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
144
9.8.6.5 Installing a Pad Power Connector
Prerequisites
Before installing a pad power connector, prepare the materials listed in
Table 9-3
Material list
Name
Exterior
Description
Pad power connector
The BOM number is
14190892.
Pad power connector
The BOM number is
14190242.
Pad power connector holder
Obtain it from the pad
mounting kit materials
(BOM number: 21242016).
Procedure
Step 1
Assemble the pad power connector holder, as shown in the following figure.
1.
Clamp the power connector to the guide rail of the holder.
2.
Install the holder cover using two M4x12 screw assemblies.
3.
Install the holder baffle plate using one M4x12 screw assembly.