FusionModule5000 Smart Modular Data Center
Installation Guide (Single-Row Aisle Containment with
2000 mm High Cabinets, ECC800)
A Appendix
Issue 01 (2019-03-05)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
226
Figure A-33
Connecting cables to the industrial connector (three-core cable)
Figure A-34
Connecting cables to the industrial connector (five-core cable)
A.7 (Optional) Connecting PDU2000 Cables
Context
If the PDU2000 is not provided with industrial connectors, connect the PDU2000 cables and
lay out the cables on the cabinet top. If new main ways are configured, connect cables to new
main ways, and then route the cables to the PDU2000s along cabinets.
Procedure
Step 1
Refer to
to connect the PDU2000 cables.
show only the cable connection methods. PDU2000 cable
connections depend on the PDU2000 type and wiring port silk screen.