74
3. Test the Project in Equinox Development Suite (Target System connected)
•
Launch the Project in Equinox Development Suite
•
With your Target System
CONNECTED
, place a Volt Meter across the Target Vcc and
GROUND terminals of the programmer (on the I/O Connector Module)
•
Click
the
<Power Up>
button in EDS
Æ
the programmer
<BUSY>
LED should now illuminate
•
Measure the voltage across the
Target_Vcc
and
GROUND
terminals of the programmer.
•
Power up the Target System
•
Measure the voltage across the
Target_Vcc
and
GROUND
on the actual Target System
•
Compare the voltage measured across the programmer output and the Target_Vcc. These
voltages should be approximately the same.
•
Try a programming operation such as
<Check Signature>