2. Test the Project in Equinox Development Suite (Target System disconnected)
•
Launch the Project in EDS (Development Mode)
•
Select
the
<Target Power Supply>
tab
Æ
the Power Supply settings are now displayed
•
With your Target System
DISCONNECTED
, place a Volt Meter across the Target Vcc (TVCC)
and GROUND terminals of the programmer (on the I/O Connector Module)
•
Click
the
<Power Up>
button in EDS
Æ
the programmer
<BUSY>
LED should now illuminate
•
The programmer should now output the specified
‘Target Voltage’
on the
‘TVCC’
pin of the
programmer IO-CON module.
Æ
the
‘Target Vcc’
LED on the I/O Connector Module should now illuminate
•
Measure the voltage across the Target Vcc
‘TVCC’
and GROUND terminals of the
programmer.
•
If the voltage is within the limits specified in the project, click
<Power Down>
to remove power
to the Target System and go to step (3).
•
If the voltage is outside the limits specified in the project, adjust the tolerance settings and
then repeat step (2).
3. Connect the Target System to the programmer
•
Connect the Target System to the programmer via an ISP Cable, Fast Connect connectors
or wire-wrap connectors.
•
Remove
the
‘Vcc Option Link’
on the I/O Connector Module (labelled J6 or J28).
•
Check that you have a zero ohm connection between
the Target Vcc
(Vout) of the
programmer and the Vcc line of the Target System.
•
Using a DVM, check that there are no shorts between the
Target_Vcc
and Target Ground
Summary of Contents for PPM3 MK2