D 39
6.3
General information on the heating system
The electric heating system is supplied
with power by a generator on board the
paver finisher which is controlled fully-
automatically in accordance with re-
quirements.
Heating resistors in the form of heating
strips ensure direct temperature transi-
tion and even distribution of heat.
Each screed section is heated by three
heating strips. Two can be found on the
bottom plate and one on the tamper
knife.
The temperature display can be called
up for the individual screed sections or
as a mean value for all sections. Tem-
perature regulation is carried out for all
screed sections together.
The heater is connected to other fitted
screed components via simple plug con-
nections.
The heating system can be operated in
an energy saving mode in which not all
heating sections are active at the same
time.
In the event of sensor failure, the heater
can continue to be operated via an
emergency programme.
The switch cabinet is equipped with an
additional 230 V socket for external con-
sumers (e.g. additional lighting).
Since fuels (gas, diesel) are not handled and insulation monitoring takes place, max-
imum possible protection of personnel is offered.
f
Beware of hot surfaces! Danger of burning!
f
Maintenance and repair work on electrical systems with medium voltage levels, e.g.
the screed heater, may only be carried out by specialist electricians or persons in-
structed in electrical engineering work if the appropriate test devices are used.
Always comply with relevant technical electrical protection precautions. Danger to life
as a result of accidents involving medium voltage levels.
Summary of Contents for V5100TV-H
Page 2: ...www dynapac com...
Page 10: ...V 2...
Page 24: ...A 2...
Page 35: ...B 11 5 o 4 7 2 1 6 2 4 o 1 3...
Page 42: ...C 4 2 1 4 3...
Page 63: ...D 21 5 Screed heater PLC version 5 1 Switch cabinet for screed heater 40 43 44 42 41...
Page 65: ...D 23 5 2 Operating the control and monitoring unit 45 46 55 47 48 49 50 53 54 51 52...
Page 78: ...D 36 6 2 Operating the control and monitoring unit 100 101 110 102 103 104 105 108 109 106 107...
Page 94: ...D 52...
Page 100: ...E 6 Transport position 5 4 6 9 12 10 11 14 15 15 14 13...
Page 128: ...E 34 6 6 Material guide plate brace 1 2 3 3 4 6 5 7 9 8 10 11 II I 4...
Page 136: ...E 42...
Page 144: ...F 8 5 2 Guide tubes 1 1 2 2 2x 1 2...
Page 148: ...F 12 6 2 Cleaning the screed Emptying the tamper compartment 1 1 2 2 2a 1a 1a 3 4 3 4...
Page 163: ...F 27 14 2 PLC version gas heater Fuses in the switch cabinet of the screed heater A Fuses A...
Page 194: ...G 22...
Page 196: ...www dynapac com...