ANNUAL INSPECTION (REGULAR INSPECTION)
The inspection shall be performed by a skilled technician or an expert inspection body with
documented evidence of competence according to requirements presented on page 10. In the
inspection special attention has to be paid to the condition of the steel structures, the safety devices
and the operating system.
Clean the lift before the inspection
The inspection incorporates the following measures and checks:
-
perform the measures of the daily and monthly inspection
-
inspect thoroughly the hydraulic system
-
power unit
-
connect the pressure gauge to the measuring point in the hydraulic system
-
make the oil flow through the relief valve by driving one of the movements
against the end stop
-
read the pressure in the gauge; when the oil is warm the pressure should be
21 - 21.5 MPa (210 - 215 bar)
-
load-holding check-valves on the outriggers
-
lift the device off the ground with the outriggers and measure the distance to
the chassis at each outrigger
-
step on the platform and extend the telescope keeping the boom level
Turn the boom round a few times, stop at the initial position and check that
the distance between the ground and the outriggers has not changed.
-
lift the outriggers from the ground and leave them in this position for about
10 minutes
Observe that the outriggers do not lower of themselves.
-
load-holding check-valve on the lift cylinder
-
lift the boom from the chassis control panel to an angle of about 45° and
extend the telescope
Observe about 10 minutes that the boom does not lower of itself.
-
load regulation valve of the telescope cylinder
-
lift the boom from the chassis control panel and extend the telescope slightly;
leave it in this position for about 5 minutes
-
make sure that the telescope does not retract of itself
-
load regulation valve of the levelling system
-
put a load of about 80 kg on the platform
-
lift and lower the boom 4 - 5 times
-
make sure that the position of the platform does not change
-
electric directional valves
-
operate all boom and turning movements and check that they all work
properly and that the movements stop as soon as the levers are released
Summary of Contents for DINO 260XT
Page 2: ...DINO 260XT 2...
Page 3: ...DINO 260XT 3 OPERATING INSTRUCTIONS Valid from serial number 26121...
Page 6: ...DINO 260XT 6 REACH DIAGRAM...
Page 12: ...DINO 260XT 12...
Page 14: ...DINO 260XT 14 28L 28 28R 13 14 12 15 6 16 1 5 32 2 29 3 31 4A 10 34 7 33 8 9 11 4B...
Page 16: ...DINO 260XT 16 30A 26 25 23 20 36 18 22 30B 35 24 19 17 21...
Page 22: ...DINO 260XT 22 28L 28 28R 13 14 12 15 6 16 1 5 32 2 29 3 31 4A 10 34 7 33 8 9 11 4B...
Page 24: ...DINO 260XT 24 24 30A 26 25 23 20 36 18 19 22 17 21 30B 35...
Page 40: ...DINO 260XT 40 LUBRICATION PLAN...
Page 42: ...DINO 260XT 42 1...
Page 81: ...DINO 260XT 81...
Page 82: ...DINO 260XT 82 ELECTRIC DIAGRAM 26094...
Page 83: ...DINO 260XT 83...
Page 84: ...DINO 260XT 84...
Page 85: ...DINO 260XT 85...
Page 86: ...DINO 260XT 86...
Page 87: ...DINO 260XT 87...
Page 88: ...DINO 260XT 88...
Page 89: ...DINO 260XT 89...
Page 90: ...DINO 260XT 90...
Page 91: ...DINO 260XT 91...
Page 92: ...DINO 260XT 92...
Page 93: ...DINO 260XT 93...
Page 94: ...DINO 260XT 94...
Page 95: ...DINO 260XT 95...
Page 96: ...DINO 260XT 96...
Page 97: ......
Page 99: ...DINO 260XT 99 HYDRAULIC DIAGRAM BOOM SYSTEM 26102...
Page 100: ...DINO 260XT 100...
Page 101: ...DINO 260XT 101 Notes...