PhaseChek™
PhaseChek
1
is a unique feature of the PowerScout series instruments that simplifies installation by
ensuring proper CT orientation and avoiding faulty data collection.
V
ERIFYING THE
P
OWER
S
COUT
™
M
ETER
S
ETUP
U
SING THE
LED
S
The PowerScout uses three bi-color PhaseChek LEDs for each element. These LEDs provide the following
information:
All LEDs are green—the system power factor is greater than 0.55 and the CTs are properly
placed on the corresponding voltage phases.
Any one LED is red—there is a phasing connection error.
Two LEDs are red and one is green—two CTs are reversed.
All three LEDs are red—all CTs are incorrectly connected.
The following table describes the PhaseChek error conditions and the appropriate correction.
1
P
atent No. 7,612,552. U.S. Patent and Trademark Office.
D
ID
Y
OU
K
NOW
?
If the total system
power factor is less than 0.55, the
LEDs will be red even if
connected properly. This
situation is rare but could occur
if, for example, the load to be
monitored is a lightly loaded
electric motor where it is
common for the power factor to
be less than 0.55 and the
corresponding LEDs will be red.
24
Shop for Dent products online at:
1.877.766.5412
www.
PowerMeterStore
.com