Chapter 3: Configuration and commissioning
1X-E4 Series Installation Manual
63
Commissioning
Before commissioning the control panel
Before commissioning the control panel, make sure that:
• The control panel has been correctly installed
• The mains power is 110 VAC or 230 VAC, is connected correctly, and
complies with all requirements described in “Connecting the mains power
supply” on page 18
• There are no short or open circuits in any of the zone circuits
• All zones have the correct end-of-line termination, as described in
“Terminating zones” on page 11
• All manual call points have the correct resistance for alarm identification, as
described in “Connecting manual call points” on page 12
• Polarity is observed for all sounder circuits and that all end-of-line resistors
are installed, as described in “Connecting sounders or other notification
devices to supervised outputs” on page 16
• Any optional equipment installed (fire routing, alarm, and fault relays, etc.) is
correctly connected
• The batteries are connected correctly, and comply with all requirements
described in “Connecting the batteries” on page 20
• All fire alarm and evacuation system configuration complies with the
corresponding operating mode and local regulations
Summary of Contents for 1X-E4 Series
Page 1: ...1X E4 Series Installation Manual P N 501 415403 1 50 ISS 13JUN22 ...
Page 76: ...Chapter 4 Maintenance 70 1X E4 Series Installation Manual ...
Page 94: ...Appendix A Configuration presets 88 1X E4 Series Installation Manual ...
Page 98: ...Appendix B Regulatory information 92 1X E4 Series Installation Manual ...