Installation & Start-Up | 3-17
3. Route the AC power conductors through the Power cable entry port
and into the Electronics Enclosure.
Terminate the AC power wires at
TB1
as detailed in the Customer
Connections drawing.
Do not apply power to the system until after all of the wiring has been
installed, connected, and verified, and only if the purging system (if
used) is ready for operation.
4. Plug all unused cable entry ports with certified plugs.
Permanent Ethernet Cable Connections (Optional)
When using the Ethernet interface on the analyzer, the minimum re-
quirements for the Ethernet cable is a CAT 5e (maximum 100 m) cable to
connect the analyzer to the network, up to a maximum of 100 m from
the hub. For outdoor analyzer installations, hazardous locations, and/or
lengths greater than 100 m, special requirements may be necessary. Con-
tact your network administrator for information.
For systems using a
permanent Ethernet connection
, a ferrite core
(Part Number 301-1044, supplied by AMETEK) must be installed
on the Ethernet cable (supplied by customer), inside the Electronics
Enclosure.
For details about setting up Ethernet parameters, refer to “Ethernet Net-
work Screen” in Chapter 4.
To install the customer Ethernet cable and ferrite core:
1. Route the Ethernet cable through one of the Signal cable entry ports
and into the Electronics Enclosure. Pull through enough cable to loop
around the ferrite.
2. Insert the Ethernet cable through the ferrite core and loop the cable
once around the ferrite, leaving enough cable length to reach the Eth-
ernet port at
J18
on the
Customer Connection
board. Adjust the cable
and ferrite so the ferrite is as close as possible to the
Customer Con-
nection
board.
Connect the cable to
J18
.
3. Route the cable to the network connection in the plant and connect it.
!
WARNING
NOTE
Summary of Contents for IPS-4-UV
Page 15: ...Contents xv...
Page 16: ...xvi IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Page 24: ...1 8 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Page 66: ...3 36 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Page 144: ...6 6 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Page 180: ...A 2 IPS 4 UV Analyzer GPDiv2 Analyzer Light Path Schematic...
Page 183: ...Appendix Drawings A 5 Detector Interface Board 100 1937...
Page 184: ...A 6 IPS 4 UV Analyzer GPDiv2 Detector Board 100 1955...
Page 185: ...Appendix Drawings A 7 Display Interface Board 100 1978...
Page 186: ...A 8 IPS 4 UV Analyzer GPDiv2 Customer Connection Board 100 1971...
Page 187: ...Appendix Drawings A 9 Relay Board 100 1942...
Page 188: ...A 10 IPS 4 UV Analyzer GPDiv2 Analog Board 100 1922...
Page 189: ...Appendix Drawings A 11 MCU Board 100 1914...
Page 190: ...A 12 IPS 4 UV Analyzer GPDiv2 Xenon Lamp Board 100 2061...
Page 191: ...Appendix Drawings A 13 Electronics Enclosure Wiring Diagram Sheet 1 of 3 WX 102877...
Page 192: ...A 14 IPS 4 UV Analyzer GPDiv2 Electronics Enclosure Wiring Diagram Sheet 2 of 3 WX 102877...
Page 193: ...Appendix Drawings A 15 Electronics Enclosure Wiring Diagram Sheet 3 of 3 WX 102877...
Page 194: ...A 16 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...
Page 196: ...S 2 IPS 4 UV Analyzer GPDiv2 This page intentionally left blank...