Chapter 5: Installing the Chassis in an Equipment Rack
120
Section II: Installing the Chassis
Removing the Shipping Brace
Now that the chassis is installed in the equipment rack, you may remove
the shipping brace from the front of the unit. To remove the shipping
brace, remove the six mounting screws with a #2 Phillips-head
screwdriver (not provided). Refer to Figure 45.
Figure 45. Removing the Shipping Brace
After removing the shipping plate, go to “Installing the Chassis Grounding
Wire” on page 121.
Shipping Brace Screws
Summary of Contents for AT-SB*81CFC960
Page 20: ...20...
Page 34: ...Chapter 1 Chassis and Power Supplies 34 Section I Hardware Overview...
Page 94: ...Chapter 3 AT SBx81CFC960 Controller Fabric Card 94 Section I Hardware Overview...
Page 96: ...96...
Page 142: ...Chapter 6 Installing the Power Supplies 142 Section II Installing the Chassis...
Page 230: ...Chapter 10 Powering On the Chassis 230 Section II Installing the Chassis...
Page 254: ...Chapter 12 Troubleshooting 254 Section II Installing the Chassis...
Page 298: ...Chapter 14 Upgrading the Controller Fabric Card 298 Section II Installing the Chassis...
Page 300: ...300...
Page 314: ...Chapter 15 VCStack Plus Overview 314 Section III Building a Stack with VCStack Plus...