84
System Manual SCK Gas Sampling System
42/23-81 EN Rev. 4
General transport information
Danger of crushing when lifting or lowering the transport unit
Only appropriately trained personnel may transport the transport units and only
with the aid of the recommended transport equipment.
Do not stand under suspended loads.
Follow the transport instructions in these operating instructions carefully.
Risk of injury in the area of the gas sampling system due to moving or fall-
ing parts, anti-freeze, lubricating oil
Wear general personal protective equipment:
Closed overalls with long trousers and long sleeves
Safety shoes
Safety gloves suitable for mechanical work
Safety glasses
Protective helmet
If necessary, additional protective equipment if prescribed by the operator.
During transport make sure that the transport packaging is not damaged or re-
moved. Observe the below-mentioned temperature and humidity limits during
transport.
In the event of transport damage attributable to improper handling, instigate dam-
age assessment by the carrier (rail, post office, and forwarder) within seven days.
Make sure that none of the enclosed accessories are lost during unpacking. Store
the screws in case the unit needs to be transported again in the future.
The retractor including the probe weighs 450–500 kg depending on the length of
the retractor and type of probe. A crane and suitable transport equipment is re-
quired for transport and unpacking. Use the transport lugs to fasten the lifting
ropes. The lifting ropes must be long enough to ensure an angle of at least 60°
under strain. Otherwise the retractor cabinet can get twisted.
If the cooling module is also transported by crane, observe the same points.
Heavy transport units
Mechanical and
material dangers
General remarks
regarding transport
Transport with crane
Summary of Contents for SCK
Page 2: ......
Page 16: ......
Page 36: ......
Page 54: ......
Page 110: ......
Page 222: ......
Page 232: ......
Page 235: ...42 23 81 EN Rev 4 System Manual SCK Gas Sampling System 235 ...
Page 236: ...236 System Manual SCK Gas Sampling System 42 23 81 EN Rev 4 Electrical connection plan ...
Page 237: ...42 23 81 EN Rev 4 System Manual SCK Gas Sampling System 237 ...
Page 238: ...238 System Manual SCK Gas Sampling System 42 23 81 EN Rev 4 Transformer connection plan ...
Page 242: ......
Page 243: ......