HVC
‐
PD
E
‐
Bus
Charger
Installation
Guide
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022 Page
83
of
146
CAN cable connection in
secondary 1 HVC 150S
:
A Terminal
block
B CAN cable to primary HVC 150
C CAN cable from secondary 2 HVC 150S (in case of a HVC 450 kW system)
1. Move the cable towards the terminal block (A).
2. Strip 0.43 Inch of the insulation from the ends of the wires.
3. Crimp a ferrule onto the end of the wire.
4. Loosen the connector screws.
5. Insert the wires into the connectors, see table below:
Functional description
Connector
Wire color
CAN H In (to primary HVC 150)
X286-1
Brown
CAN L In (to primary HVC 150)
X286-2
White
CAN GND (to primary HVC 150)
X286-3 or Shield Can In
Shield
CAN H Out (from secondary 2 HVC 150S)
X286-16
Brown
CAN L Out (from secondary 2 HVC 150S)
X286-17
White
CAN GND (from secondary 2 HVC 150S)
X286-18 or Shield Can Out
Shield
See also Appendix H
Signal connection diagram
.
6.
Tighten the connector screws with a tightening torque of 1.0 ft-lb.