HVC
‐
PD
E
‐
Bus
Charger
Installation
Guide
Document: V1.2 / Document No.: 6AGA000008-0629-EN | Date: 06-30-2022 Page
4
of
146
Table of Contents
1.
Introduction
9
1.1.
Preface
9
1.2.
Intended document users
9
1.3.
Signs
9
1.4.
Safety regulations
10
1.4.1.
Owner responsibilities
10
1.4.2.
Tilting and handling
11
1.4.3.
Electric hazards
12
1.4.4.
Installation safety
12
1.5.
Environment and disposal of waste
13
1.6.
Cyber Security Disclaimer
13
1.7.
Contact information
14
2.
Description of the product
15
2.1.
Overview of the system
15
2.1.1.
Standard HVC-PD 150 kW E-Bus Charger system
15
2.1.2.
Standard HVC-PD 300 kW E-Bus Charger system
16
2.1.3.
Standard HVC-PD 450 kW E-Bus Charger system
16
2.1.4.
Power Cabinet
17
2.1.5.
ACS Control Module
18
2.1.6.
Junction Box
19
2.1.7.
Charge pole
19
2.2.
Accessories
20
2.2.1.
Foundation for Power Cabinet
20
2.2.2.
Foundation for Charge pole construction
21
2.2.3.
Communication glass fiber cable
22
2.2.4.
RFID unit
23
2.3.
Project planning
24
3.
Preparation
25
3.1.
About preparation
25
3.2.
Permits
26
3.2.1.
Power connection
26
3.2.2.
Construction permit
26
3.2.3.
Internet access
26
3.3.
Upgrade grid
27
3.4.
Location
27
3.5.
Geometry of infrastructure
28
3.5.1.
Required space for the Power Cabinet
28
3.5.2.
Placement of multiple cabinets
29
3.5.3.
Required space for the Charge pole
30
3.6.
Pole position in relation to the bus
31
3.6.1.
Pole position in relation to the drive direction of the bus
32
3.6.2.
Pole position in sideways direction of the bus
32
3.6.3.
Maximum slope of the road in X-axis
34
3.6.4.
Maximum slope of the road in Z-axis
35
3.7.
Electrical engineering
36
3.7.1.
Electrical installation
36
3.8.
Civil installation
36
3.9.
Lightning protection
37
4.
Construction
38