5.8.6. Connect the CAN cable
NOTICE
The CAN cable connection is only needed for the HVC 300 kW and 450
kW E-Bus Charger, see for more details section
Cabling
on Page 49.
CAN cable connection in
secondary 2
HVC 150S
(in case of a HVC 450 kW system):
A Terminal
block
B CAN cable to secondary 1 HVC 150S
1. Move the cable towards the terminal block (A).
2. Strip 0.43 of the insulation from the ends of the wires.
3. Crimp a ferrule onto the end of the wire.
4. Loosen the connector screws.
5. Insert the wires into the connectors, see table below:
Functional description
Connector
Wire color
CAN H Out
X286-10
Brown
CAN L Out
X286-11
White
CAN GND
X286-12 or Shield Can Out
Shield
See also Appendix H
Signal connection diagram
.
6.
Tighten the connector screws with a tightening torque of 1.0 ft-lb.