VERSUM MATERIALS, INC. APx DISTRIBUTION SYSTEM FIELD START-UP CHECKLIST
page 2 of
8
ELECTRICAL
Check off line item when completed
Sign and date when section is completed
Branch 1-4 (A-D)
Branch 5-8 (E-H)
Earth ground installed
120v/240v electrical complete (circle)
Graphics panel condition satisfactory
Elect. sealoffs poured
I/O wired per DWG # EE-
series
Verify heat tape power
SECTION COMPLETED SIGNATURE
DATE
CONTROLLER
Branch 1-4 (A-D)
Branch 5-8 (E-H)
Seat all circuit boards, eproms and ribbon cable
connections ( caution: remove power before
removing eproms or circuit boards)
E-stop guard in place
Remove pneumatic bulkheads from the back of the controller.
Do all valves operate ?
Manual mode operation
No audible solenoid leaks
Re-install pneumatic bulkheads from the back of the controller.
Firmware versions:
Core
Display
I / O
Network
Core boot loader
Display Boot Loader
Configuration File Rev.
External Shutdown wired
Supervisory circuit utilized
Correct program loaded / version
Program name and date
Life safety system utilized ( yes / no )
Life safety system contact N.O. ( yes / no )
Barriers installed per controller item # verification
SEMC See attached GASGUARD inspection and test
sheet
Shorting blocks per controller item # verification
SEMC See attached GASGUARD inspection and test
sheet