84 • Packing, Storage, Handling and Assembly
_____________________________________________________________________________________________
9.
PACKING, STORAGE, HANDLING AND ASSEMBLY
Note!
This section only refers to standard cabinet!
For other than standard cabinet design refer to the supplied drawings and/or
consult the factory.
9.1
Packing Specification
Equipment is packed and covered and placed on the case base of the crate.
Crate side walls 8mm thick playwood and 20x90mm beams
Crate is closed by pins and metal band
Crate is marked by international marks
Wood is marked in according to ISPM 15
9.2
Storage
The soft starter is designed for indoor use and must not be left outdoors.
Soft starter should be stored in a warm, dry room and protected against dust and debris.
If the soft starter is to be kept in store before use make sure that the ambient conditions are acceptable:
Storing temperature:
-20…..+70°C
Relative humidity:
<95%, no condensation.
9.3
Handling
The cabinet is delivered in its crate. See weights and dimensions below.
The crates can be off loaded by forklift truck.
Off load the soft starter using an overhead crane (see below scheme).
Approximate
weights and dimensions
Unpacked
Packed
Width
[mm]
Height
[mm]
Depth
[mm]
Weight
[kg]
Width
[mm]
Height
[mm]
Depth
[mm]
Weight
[kg]
1100 2300
(1)
1100 600 1200 2500 1200 660
Notes:
(1) Add 65mm for eye bolt.
(2) Each eye bolt can carry 700kg max.
Each cabinet, after unpacked, must be lifted using 4 eye bolts as shown on the pictures below.
Use 1100mm cables for each eye bolt, make sure top angle
≤
60°.
Figure 23 – Eye Bolts Location on Top of the Cabinet
Use the marked eye bolts for lifting the cabinet.
During lifting procedures it is mandatory to use ALL lifting eye bolts provided on each cabinet.