4 Commissioning a new Installation
•
This section provides a guide to the steps that are required to commission a new installation.
•
Precise details on how to perform each step, and on the functionality of each programming option, are given in
appropriate sections of this manual.
4.1 Step 1 – General Setup
•
Ensure that the panel configuration memory is cleared and returned to factory settings. Refer to TIME / DATE –
SYSTEM CLEAR OPTION on Page 2 of the Commissioning Menus.
•
Select the SETUP OPTION from Page 3 of the Commissioning Menus. Press
YES
to step through each item to
inspect the factory default settings and to make changes as required. For example, to enter service telephone
number and company name.
4.2 Step 2 – Configure Each Signaling Loop
•
Select the CONFIGURE option from Page 1 of the Commission Menus and then perform the following.
1. Select “Signaling Loop 1”.
2. Perform an “Auto Learn”.
3. Select “Devices” and change sensor location text as required.
4. Assign Zones.
•
Repeat actions 1-4 above for each signaling loop connected to the panel.
•
Enter Zone descriptions.
•
NOTE: If using a PC to program the panel, actions 3 and 4 above will already have been defined on the PC.
4.3 Step 3 – Configure Peripherals (if required)
•
Select the CONFIGURE option from Page 1 of the Commission Menus and then perform the following.
1. Select “Peripheral”.
2. Perform an “Auto Learn”.
3. Select “Devices” and change the units’ location text as required.
4. Assign Zones and set the operation of the unit.
4.4 Step 4 – Configure Outputs (sounders and relays)
•
Select the CONFIGURE option from Page 1 of the Commission Menus and then perform the following.
1. Select “Sounders”, if zonal ringing patterns are required and program accordingly.
2. Select “Relays”, if zonal operation is required and program accordingly.
•
Finally, select the INSPECT option from Page 1 of the Commission Menus. Compare the commissioning data
entered against the installation sheets. This facility allows the data to be inspected without risking any inadvertent
changes.