SET UP PROCEDURE
The mechanical and electrical connections are completely
checked out, apply power to the DigiPackⅡ. Do not apply
hydraulic power at this time.
The DigiPackⅡLCD will light up and the F1 Profile appear
after an interim screen. Then press F4+Set key to set the
Machine setting to reflect language, servovalve type, machine
type. The Machine settings made earlier may also be seen as
the language used on the LCD, and the LED indicating either
a Continuous or an Accumulator blow molding machine.
To go to Set Up mode press and hold F1 Profile and then
press Set. The Set Up mode screen appears as shown in
“
Figure 1-34
”.
Three words appear on the left side of the screen, DCDT / SSI, Accumulator and Gain. The setup functions
for DCDT / SSI, Accumulator and Gain are controlled by this screen. The highlighted word, in this case
DCDT / SSI, indicates the setup screen to be accessed when SET is pressed. Note that. Accumulator will
appear only when the Machine setting (F4+Set) are set for an Accumulator blow molding machine.
Each of the screens for DCDT / SSI, Accumulator and Gain has the word “Back” at the end of the setup
procedure for that screen. Pressing SET when Back is highlighted will return the display to the SETUP
screen.
Figure 1-34 Tooling SET
UP Mode