8 Commissioning Core Components
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
82
Center
>
iManager NetEco 6000
license of the NetEco software by referring to the guide.
8.4.1.3 Powering On a Server
This section describes how to check and power on the NetEco server before powering on it.
Procedure
Step 1
Ensure that the power cables and ground cables are securely connected with correct polarity
and good contact.
Step 2
Ensure that the input power supply for the AC PDB is off. Use a multimeter to test the
resistance between the power outputs of the AC PDB and between the BGND and PGND. It
is required that short circuit not occur between power outputs or between the BGND and
PGND.
Step 3
Switch on the power of a rack.
Step 4
Switch on the circuit breakers of PDBs for the rack. The power supply for equipment in the
rack is available.
Step 5
Press the power button on the chassis of the server to power on the server.
After the server is started properly, the button/indicator of its power switch is displayed green.
The 2288H V5 server is used as an example. The following figure shows the power button of
the 2288H V5 server.
Figure 8-13
2288H V5 power button
----End
8.4.1.4 Logging In to the PowerEcho
The PowerEcho uses the browser/server (B/S) working mode. You can manage and maintain
the NetEco system server after logging in to the PowerEcho over the browser on a PC.
Prerequisites
The browser version is Internet Explorer 11, Firefox 38ESR, Firefox 60ESR, Chrome 50
and Chrome 68.