FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
4 Preparations for Power-On Commissioning
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
20
Field
Personnel Skill Requirement
system
data center, familiar with basic communications protocols, familiar
with equipment interfaces in weak-current systems, and proficient in
operating the NetEco management system
With weak-current engineer qualifications
Fire extinguishing
system
Familiar with the fire extinguishing system configurations and the
operations for each core device in the FusionModule1000
With fire protection engineer qualifications
Lighting and
structural systems
Familiar with the overall configurations and layout of the
FusionModule1000
Experienced in data center maintenance
4.4 Preparing for the Power Supply and Distribution
System Power-On Commissioning
Prerequisites
The FusionModule1000 has been installed and has passed the insulation test.
Preparations
Tools: multimeter, phillips screwdriver
Documents: power supply and distribution device layout diagram, power supply and
distribution system diagram, power supply and distribution device initial configuration table
Skill requirement: power distribution engineer
For the diagrams and tables, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
Understand the layout of the power supply and distribution devices by referring to the power
supply and distribution device layout diagram.
Step 2
Understand the control relationship of the power supply and distribution system by referring
to the power supply and distribution system diagram.
Step 3
Understand the initial configurations of the power supply and distribution system by referring
to the power supply and distribution device initial configuration table.
----End