FusionModule1000A40 Prefabricated All-in-One Data
Center
Commissioning Guide
8 Commissioning Core Components
Issue 02 (2019-12-20)
Copyright © Huawei Technologies Co., Ltd.
111
8.5.1.2 Commissioning the Emergency Lights (standard)
Prerequisites
The sockets of the emergency light have been powered on.
Preparations
Tools: step ladder, needle-shaped tool
Documents required: power supply and distribution system diagrams, fire extinguishing
device layout diagram (standard)
Skill requirement: fire engineer
For the diagrams, see the initial configuration parameter manual for the solution in use.
Procedure
Step 1
When you press down the
TEST
button on the emergency light, the emergency light turns on.
When you release the
TEST
button, the emergency light turns off.
Step 2
When you unplug the power plug of the emergency light, the emergency light turns on. When
you stab the small hole shown in the figure with a needle-shaped tool, the emergency light
turns off.
You can also turn off the emergency light by pressing and holding the
TEST
button for more than
5s.
If the result expected for each step appears, the emergency light is working properly.
Figure 8-35
Small hole in the emergency light
----End