UPS5000-H-1200 kVA
User Manual (100 kVA Power Modules)
3 Installation
Issue 01 (2020-07-15)
Copyright © Huawei Technologies Co., Ltd.
53
Tools and Meters
Phillips screwdriver
(M3/M4/M5/M6/M
8)
Insulated torque
wrench
(M6/M8/M12/M16)
Heat shrink tubing
Insulated adjustable
wrench
Table 3-1 lists only the common tools for installation and cable connection. For more dedicated tools
required, see the corresponding component manuals. Prepare tools based on site requirements.
3.1.3 Preparing Power Cables and Copper Bars
The UPS can generate large leakage currents. A circuit breaker equipped with a residual
current device (RCD) is not recommended.
Copper bars need to be prepared for the mains input, bypass input, and output, and cannot
be directly connected using cables.
Prepare mains input, bypass input, and output copper bars based on the following drawings
and current requirements.