UPS5000-E-(350 kVA-800 kVA)
User Manual (50 kVA Power Modules)
5 Operations
Issue 05 (2018-01-08)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
236
5
Operations
5.1 Powering On and Starting the UPS
5.1.1 Powering On the UPS
Prerequisites
Measure the voltage and frequency of the UPS input switch and upstream input switch.
Voltage range: 138–485 V AC (line voltage); frequency range: 40–70 Hz.
Context
The following operations are applicable to a single UPS. For parallel systems, contact
Huawei technical support.
Before powering on the UPS, ensure that the UPS has passed all check items in the
section "Installation Verification."
Before powering on the UPS, ensure that all the UPS switches and upstream switch are
OFF.
Procedure
Step 1
Close the upstream bypass and mains input switches.
Step 2
(Full configuration model) Close the UPS bypass input switch, mains input switch, and output
switch.
After the UPS is powered on, initialization begins. The MDU displays the Huawei logo and
an initialization progress bar.
----End
5.1.2 Starting the Inverter
Table 5-1
UPS system user list
Default User
Preset Password
admin (administrator)
LCD
000001