Figure 3-78
Removing the top cable covers and drilling holes
(1) Battery cable cover
(2) Power cable covers
(3) Signal cable hole
Step 3
Remove the rear cover from the bypass cabinet.
You are advised to remove the side panel from the bypass cabinet before connecting cables.
Step 4
Remove the copper bars between the mains and bypass inputs. (Perform this step only when
the mains input and bypass input use different power sources.)
Properly keep the removed copper bars and bolts.
(Optional) If copper bar protective covers are installed for the bypass cabinet, remove the protective
covers and then the connecting copper bars. The protective covers need to be reinstalled after the