Installation Preparations
2.1 Unpacking and Acceptance
Unpack and inspect all cabinets, mechanical parts, and components. Check that all
the items are intact and comply with the packing list on the presence of both the
project supervisor and customer.
Procedure
Step 1 Unpack the carton labeled Contain Packing List and take out the
Packing List
.
Step 2 Check all items against the
Packing List
.
Step 3 If shortage or miscarriage occurs, fill in the
Cargo Shortage and Miscarriage
Report
.
Step 4 If cargo damage occurs, fill in the
Cargo Replacement Application Form
.
Step 5 Sign on the
Packing List
with the customer after verifying that all required items
are delivered.
Step 6 Store the items properly.
----End
Follow-up Procedure
Put the items to be installed immediately onto an ESD surface, such as a
polyethylene (PE) bag or an expandable polyethylene (EPE) foam. Pack the items
not to be installed immediately with their original packing materials. Put them in
a dry and cool environment without exposure to sunlight or electromagnetic
radiation.
2.2 Tools and Instruments
Before the installation, prepare the following common tools and transportation
tools. Tools required vary with the actual installation scenarios.