Verify remaining Heat Exchanger fan rotation. Repeat above step for 2nd (and 3rd if
used) fan.
2.11.1 Initial System Leak Tests
Turn on pump A for several minutes. Upon the establishment of a steady (no air
bursts) volume of water throughout the system, begin visual check for leaks. Turn off
Pump A after thorough leak checks.
Turn on pump B for several minutes. Upon the establishment of a steady (no air
bursts) volume of water throughout the system, continue visual check for leaks. Turn
off Pump B after thorough leak checks.
!
CAUTION:
THE SYSTEM MUST BE TESTED FOR LEAKS AGAIN ONCE THE REQUIRED 50/50
GLYCOL/WATER MIXTURE HAS FILLED THE ENTIRE SYSTEM LATER IN THE
INSTALLATION PROCESS.
Check immediately for any leaks at the following cooling system points.
•
Transmitter inlet and outlet pipe connections
•
Pump module inlet and outlet pipe connections
•
Heat exchanger inlet and outlet pipe connections
•
Test Load valve connections
•
Test Load Flow Switch inlet and outlet pipe connections
•
All solder joints, system valves and drain valves
Repair any detected leaks. If leaks have developed, and depending upon the given
leak’s personality, some water may have to be drained from the system before making
repairs.
2.11.2 Initial System Cleaning
Once the cooling system has been determined to be free of leaks it will have to be
cleaned and flushed before continuing the installation.
Create cleansing solution. Using a mixture of water (see section B.1 Coolant and
Water Recommendations in Appendix B) and a cleaning solution (a mixture of 4 cups
Содержание ATLAS ANALOGUE
Страница 4: ...iv 888 2523 001 7 26 05 WARNING Disconnect primary power prior to servicing...
Страница 6: ...vi 888 2523 001 7 26 05 WARNING Disconnect primary power prior to servicing...
Страница 8: ...viii 888 2523 001 7 26 05 WARNING Disconnect primary power prior to servicing...
Страница 10: ...x 888 2523 001 7 26 05 WARNING Disconnect primary power prior to servicing...
Страница 14: ...Table of Contents continued 4...
Страница 114: ...3 40 888 2523 001 7 26 05 WARNING Disconnect primary power prior to servicing Section 3 Operation ATLAS Analogue...