MDE-4334C Atlas Start-up and Service Manual · April 2008
Page 3-1
Introduction
Start-up Procedures
3 – Start-up Procedures
Introduction
Purpose
Gasboy Atlas units require this start-up process for pumps and dispensers that are installed in
the United States. This procedure ensures that the equipment is installed and the warranty is
registered properly. It is also recommended that you follow this procedure outside the United
States.
The start-up process and checklists are used to ensure that the unit(s) are installed and function
properly.
Important Information about Releases
Sections of this manual may be released independently of each other to supply the most
current data. Information about release date and version for independently released sections
will be included in the section title and footer of the document. Refer to the Gilbarco Online
document resource “GOLD” for the latest update.
This section was last updated in January 2007.
Topics in this Section
Topic
Page
Certificate of Conformance (CoC) Numbers
How to Use this Section
and use the instructions to ensure that all units have been
installed correctly and function properly.
Certificate of Conformance (CoC) Numbers
CoC numbers are required during installation and start-up of new sites. You may be asked for
these numbers by a Weights and Measures official. Refer to the cover page of this document
for information on CoC numbers.