5 Commissioning
5.1 Before commissioning / configuring the boiler
The boiler must be adjusted to the heating system during commissioning.
NOTICE
Optimum efficiency and efficient, low-emission operation can only be guaranteed
if the system is set up by trained professionals and the standard factory settings
are observed.
Take the following precautions:
❒ Initial startup should be carried out with an authorised installer or with Froling
customer services
❒ Turn on the main switch
❒ Set the boiler controller to the system type.
❒ Load the boiler default values.
NOTICE! For the keypad layout and instructions for modifying the parameters, see the
instruction manual for the boiler controller.
❒ Check the system pressure of the heating system.
❒ Check that the heating system is fully vented.
❒ Check that the safety devices are present and working efficiently.
❒ Check that there is sufficient ventilation in the boiler room.
❒ Check the seal of the boiler.
➥ All doors and inspection openings must be tightly sealed.
❒ Check that the drives and servo motors are working and turning in the right direc‐
tion.
❒ Check that the door contact switch is working efficiently.
NOTICE! Check the digital and analog inputs and outputs - See the instruction manual
for the boiler controller.
5
Commissioning
Before commissioning / configuring the boiler
62