35
PE cable to the grounding bar. (see the 1
st
graph in Figure 3-29) Set
up the cables referring to Figure 3-30.
Pre-insulated end ferrule
5pcs
Pre-insulated end ferrule
Core wire
Figure 3-30 Connect the PE cable to the internal grounding bar
(
2
)
Connect the AC (L1, L2, L3, N) cables to the terminal block and use
the OT type terminal to connect the PE cable to the internal
grounding stud inside the wiring box. (see the 2
nd
graph in Figure
3-29) Set up the cables referring to Figure 3-31.
Pre-insulated end ferrule
4pcs
Pre-insulated end ferrule
Core wire
OT type terminal
Core wire
OT type terminal,1pcs
Figure 3-31 Connect the PE cable to the internal grounding stud
(
3
)
Connect the AC (L1, L2, L3, N) cables to the terminal block and use
the OT type terminal to connect the PE cable to the external
Содержание CPS SCA20KTL-DO
Страница 1: ...CPS SCA Series Grid tied PV Inverter CPS SCA20 25KTL DO Installation and Operation Manual Ver 1 0 ...
Страница 18: ...14 3 2 Mechanical installation 1 Dimensions Figure 3 2 Dimensions of CPS SCA20 25KTL DO series inverter ...
Страница 56: ...52 Figure 3 48 The ZigBee cable connection a b c d e ...
Страница 97: ...93 1 5 2 4 3 ...
Страница 98: ...94 Figure 7 1 Replace cooling fans 50 60mm mm 50 60mm mm 6 ...