E1200 HT 260-3
8BMaintenance
23.04.07
9-44
00401010_41087
9.4.2.3
Installing the Vacuum Process Tube without Back Flange
Use only process tubes calibrated in accordance with the centrotherm drawing.
Otherwise, due to the different expansion factors the process tube may be destroyed in
the flange area during the heating-up.
Keep ready for the installation:
—
quartz parts for thermocouple and tube case
—
insulating rings
—
all O-rings
—
VCR seals
Proceed as follows to install the process tube:
1. De-energize the heating after baking out the heating cassette, then wait until the
heating cassette has cooled down to room temperature.
2. Pull the spike thermocouples back by 10 mm at the heating cassette.
3. Use foil or other suitable materials to cover the process tube openings to avoid
process tube contamination.
4. Install the insulating ring at the toxic gas exhaust side.
5. Slide the process tube into the heating cassette.
6. The process tube must be positioned in the heating cassette as follows:
—
centrically towards the flange on the toxic gas exhaust side
—
protruding 15 mm over the vacuum base flange into the toxic gas exhaust
—
the position of the connections at the process tube aligned according to
drawing, see chapter 12.2 Drawings, Circuit Diagrams, Overviews, page 12-1
—
at the backside centrically towards the covering plate
—
horizontally aligned, use spirit level to check
7. Avoid hollows to achieve good insulation.
8. Clean all flange parts and O-rings before installing them.
9. Slide the O-ring over the process tube.
10. Insert packing cord into the flange.
11. Slide the flange onto the centering pins and manually tighten the nuts. The process
tube is moved backwards into the correct position.
12. Connect the water and gas supply lines to the flange.
Содержание E1200 HT 260-3
Страница 1: ...Operating Instructions for Horizontal Furnace Equipment E1200 HT 260 3 Version 1 0 1_41087 11 ...
Страница 2: ...E1200 HT 260 3 23 04 07 00401010_41087 ...
Страница 4: ...E1200 HT 260 3 Document Information 23 04 07 00401010_41087 ...
Страница 16: ...E1200 HT 260 3 Index 23 04 07 00401010_41087 ...
Страница 18: ...E1200 HT 260 3 List of Figures 23 04 07 00401010_41087 ...
Страница 20: ...E1200 HT 260 3 List of Tables 23 04 07 00401010_41087 ...
Страница 26: ...E1200 HT 260 3 0BOperating Instruction Remarks 23 04 07 1 6 00401010_41087 ...
Страница 34: ...E1200 HT 260 3 1BIntroduction 23 04 07 2 8 00401010_41087 ...
Страница 50: ...E1200 HT 260 3 2BSafety 23 04 07 3 16 00401010_41087 ...
Страница 78: ...E1200 HT 260 3 4BTransport 23 04 07 5 4 00401010_41087 ...
Страница 180: ...E1200 HT 260 3 8BMaintenance 23 04 07 9 76 00401010_41087 ...
Страница 228: ...E1200 HT 260 3 10BSpare and Wearing Parts 23 04 07 11 2 00401010_41087 ...