E1200 HT 260-3
8BMaintenance
23.04.07
00401010_41087
9-45
13. Install the insulating ring at the gas cabinet side. Avoid changing the process tube
position during installation. The insulating ring must be flush mounted against the
heating cassette. If necessary, adapt the insulating ring.
14. Install the covering plate on the gas cabinet side.
15. Avoid hollows.
16. Firmly tighten the screws of the flange.
17. Open the water supply for the flange cooling and check for leaks.
18. Slide the spike thermocouples into the heating cassette until they touch the
process tube. Use spring clips to secure the spike thermocouples against sliding
out.
19. Install the tube case.
20. Install the profiling thermocouple, see chapter 9.5.3 Installing a Profiling
Thermocouple in Vacuum Systems, page 9-54.
21. Use VCR seals when connecting the gas supply to the connections at the process
tube.
22. Install the suction flange.
23. Install the bellow and the seals of the vacuum suction pipe.
24. Install the tube door, see chapter 9.4.3.3 Installing the Tube Closure - Vacuum
System, page 9-52.
25. Install the paddle and adjust the position with regard to the process tube, see
chapter 9.9 Aligning the Softlanding-System (SLS), page 9-63.
26. Switch on the heating and slowly heat up the process tube in steps of 3 - 5 °C/min,
please refer to the suppliers' documents listed in chapter 12.10 Suppliers'
Documents, page 12-4.
27. Measure the heating currents.
28. Carry out a vacuum leakage test. The leak rate during this test may not exceed
>2 mTorr/min.
Содержание E1200 HT 260-3
Страница 1: ...Operating Instructions for Horizontal Furnace Equipment E1200 HT 260 3 Version 1 0 1_41087 11 ...
Страница 2: ...E1200 HT 260 3 23 04 07 00401010_41087 ...
Страница 4: ...E1200 HT 260 3 Document Information 23 04 07 00401010_41087 ...
Страница 16: ...E1200 HT 260 3 Index 23 04 07 00401010_41087 ...
Страница 18: ...E1200 HT 260 3 List of Figures 23 04 07 00401010_41087 ...
Страница 20: ...E1200 HT 260 3 List of Tables 23 04 07 00401010_41087 ...
Страница 26: ...E1200 HT 260 3 0BOperating Instruction Remarks 23 04 07 1 6 00401010_41087 ...
Страница 34: ...E1200 HT 260 3 1BIntroduction 23 04 07 2 8 00401010_41087 ...
Страница 50: ...E1200 HT 260 3 2BSafety 23 04 07 3 16 00401010_41087 ...
Страница 78: ...E1200 HT 260 3 4BTransport 23 04 07 5 4 00401010_41087 ...
Страница 180: ...E1200 HT 260 3 8BMaintenance 23 04 07 9 76 00401010_41087 ...
Страница 228: ...E1200 HT 260 3 10BSpare and Wearing Parts 23 04 07 11 2 00401010_41087 ...