Installation
55/ 122
Powerlift prefabricated pumping station
Item Work
Description
Chapter
8
Installing the control
3.5.3
9
Connecting the air bubble injection (optional)
3.5.9
–
Installing ex-barrier (optional)
3.5.11
3.5.2 Supplying heating (optional) and work plug socket
(optional) with current
Î
Observe the connection values with electrical installations: 400 V, 50 HZ, fuse 25 A
3.5.3 Installing the control
Mounting on a wall
Specifications:
■
Flood-proof and free wall surface area of a minimum of:
MultiControl Duo Control: 400 mm x 400 mm (Width x Height)
Level Control PS 2 Control System: Dimensions as project-related on request
■
Select the maximum spacing according to the lengths of the connection cables of the
pumps and level sensor and/or control cable for level sensor. If necessary, versions
with longer connection cables or control cable can be purchased from ACO as optional
components.
Installation in the outdoor cabinet
Chapter 3.3.10 “Outdoor cabinet installation”
3.5.4 Connecting the control to the power supply
Note when executing the electrical installation:
Î
Always observe the connected value:
■
Chapter 6.4. “MultiControl Duo Control”
■
Chapter 6.5 “Level Control PS 2 Control System”