Installation
32/ 122
Powerlift prefabricated pumping station
■
Installation,
product-accompanying documentation: Instruction "Multitop manhole
cover".
Î
Clean and moisten the sliding rebate of
the cover plate and/or the supporting
ring and the underside of the cover.
Î
Apply mortar bed on the surface of the
rebate.
Î
Insert the cover in the "retainer" and
align.
3.3.6 Laying and connecting the on-site inlet pipe
IMPORTANT
Before the inlet pipe is connected, the excavations must be filled up to this level,
Chapter 3.3.11 “Backfill excavations”.
Specifications:
■
Pipe nominal width,
Chapter 6.1.1 “Dimensions”.
■
Lay pipes to be frost resistant.
■
The pipe cross-section must not reduce in the direction of flow.
■
Make flexible pipe joints.
■
Lay up to the tank with a gradient of at least 1.5 – 2 %.
■
Reverse gradients, and the formation of siphons or pockets are not allowed.
■
Select material that is resistant to the wastewater (e.g. KML, PP, PE, PVC).
Î
Use acid-free lubricant to grease the
spigot of the inlet pipe and the sealing
lips of the socket seal.
Î
Push the spigot into the socket seal.
3.3.7 Laying and connecting the on-site ventilation pipe
IMPORTANT
Before the on-site ventilation pipe is connected, the excavations must be
backfilled up to this level, Chapter 3.3.11 “Backfill excavations”.
Specifications:
■
Pipe nominal widths DN/OD = 110 mm and/or DN/OD = 160 mm with PSD-B-2200/
T
Basin
585
■
Lay the vent stack so that it rises continuously. Do not reduce the stack cross-section.
■
The vent stack pipe must not be merged with the vent stack of a grease separator.
■
The end of the vent stack must be routed to above the roof or, for example, in the
ground, where it does not cause any odour nuisance.