Sonnen sonnenBatterie 10 Installation Instructions Manual Download Page 38

6 | Connecting the storage system

38 / 100

Installation instructions sonnenBatterie 10

6.4.2 Configuring the power meter

Prerequisite:

ü

 The power meter must be disconnected from the voltage supply in order to mount the

touch display.

Tools:

• Touch display for power meter WM271

The power meter only provides correct measured values when the right measurement
mode is activated on the device. The 

single-phase

 measurement mode is the default set-

ting. With a three-phase grid, then, the measurement mode must be switched to three-
phase measurement.

power meter
WM 271

Strommessung

Erzeugung

Verbrauch

Current Measurement

Generation

Consumption

Voltage Metering

Spannungsmessung

1

2

3

4

5

6

A1 A2

13 14 15 16

Illustration 12: Removing the front cover

„

Press the clips (2) on both sides of the power
meter. You might use a small screwdriver.

„

Remove the front cover (1).

A1 A2

13 14 15 16

Illustration 13: Inserting the touch display

„

Insert the touch display (1) into the power
meter.

„

Supply the power meter with energy.

1

2

3

4

5

6

Illustration 14: Touch display

„

Press 

 for 3 seconds.

The 

PASS ?

 screen appears.

1

2

3

4

5

6

Illustration 15: Password entry screen

„

Press 

 for 3 seconds.

The 

CnGPASS

 screen appears. The power meter is

now in programming mode.

1

2

3

4

5

6

Illustration 16: CnGPASS screen

„

Press 

 once.

The 

SYS

 screen appears.

Summary of Contents for sonnenBatterie 10

Page 1: ...Installation instructions for electricians sonnenBatterie 10 with sonnenProtect 4000 optional KD 557 Part no 1000241 Version 02 info sonnen de sonnen de ...

Page 2: ...nfo sonnen de Document Document number 557 Part number 1000241 Version 02 Valid for AU NZ Publication date 18 09 2019 161236107 IMPORTANT Read this documentation carefully before installation operation Retain this document for reference purposes EN Installation instructions sonnenBatterie 10 ...

Page 3: ...g for transport damage 13 3 2 4 Transport to the installation location 14 3 2 5 Acclimating the power module before installation 14 4 Product description 15 4 1 System components 15 4 2 Scope of delivery 17 4 3 Type plate 19 4 4 Optional accessories 19 4 5 Additional parts and tools required 20 5 Installing the storage system 22 5 1 Selecting the installation location 22 5 1 1 Observing minimum di...

Page 4: ...1 7 2 Connecting the extension cabinet 52 7 2 1 Positioning the battery modules 52 7 2 2 Connecting the BMS communication lines 52 7 2 3 Connecting the battery cables 53 7 3 Completing the extension cabinet installation 54 8 Using digital inputs outputs optional 55 8 1 Overview of digital inputs and outputs 55 8 2 Connecting digital inputs outputs 56 8 2 1 Implementing PV reduction 56 8 2 2 Using ...

Page 5: ...m on 79 11 2 Carrying out first time commissioning 79 11 2 1 Commissioning assistant 79 11 2 2 Filling in the commissioning report 81 11 2 3 Taking photos to document installation 81 12 Decommissioning 82 12 1 Switching the storage system off 82 12 2 Switching the storage system off to electrically isolate it 83 13 Troubleshooting 84 13 1 sonnenBatterie 10 84 13 2 sonnenProtect 4000 optional 85 14...

Page 6: ...n this document sonnenBatterie 10 Storage system sonnenProtect 4000 sonnenProtect Licensed electrician Installer Customer who purchased the storage system Operator 1 3 Explanation of symbols DANGER Extremely dangerous situation leading to certain death or serious injury if the safety information is not observed WARNING Dangerous situation leading to potential death or serious injury if the safety ...

Page 7: ...ination An appropriate and readily accessible disconnect device shall be incorporated in the fixed wiring Repairs to the storage system must be carried out by an authorised service technician only The replacement of battery modules must be performed by authorised service techni cians only When replacing batteries replace with the same type and number of batter ies or battery modules Especially the...

Page 8: ... its original state without any user modifications and only when in perfect working order The sonnenProtect must only be connected to the storage system as described here The interfaces of the sonnenProtect and the storage system must be connected in ac cordance with the product documentation Generators e g a PV system must never be connected to the output line AC line to backup circuit see Overvi...

Page 9: ...battery modules The battery modules compatible with the storage system are protected by multiple pro tective devices and are safe when used properly Improper use or a fault may cause the battery cells inside the battery modules to be damaged This can have the following effects High heat generation on the surface of the battery cells Leaking of electrolyte vapours and or smoke The escaping electrol...

Page 10: ...r In the case of irritation of the skin eyes or mucous membranes consult a doctor 3 Contact the fire services 4 Contact the sonnen service team 61 13 7666 There is a danger of electrocution when extinguishing a fire while the storage system is switched on In the event of a fire in the vicinity of the product or in the storage system it self proceed as follows before beginning any extinguishing mea...

Page 11: ...me Warning flammable materials Warning hazards due to batteries kg Warning product is heavy CE mark The product meets the requirements of the applicable EU directives WEEE mark The product must not be disposed of in household waste dispose of it through environmentally friendly collection centres Observe the documentation The documentation contains safety information Protective earthing Labelling ...

Page 12: ...is charge could damage or destroy the battery modules For this reason the battery modules can only be stored for a limited amount of time Observe the following points The battery modules must be charged to 30 charging status upon delivery when stored Store the battery modules for no longer than 6 months Install the battery modules in the storage system after 6 months at the most and com mission th...

Page 13: ...n of toxic substances Check each battery module for transport damage ð If damage deformation defects emission of substances and the like is discovered Never use damaged battery modules Check each delivery upon arrival in the presence of the shipping agent for complete ness and damage Transport indicator on the packaging Illustration 1 Transport indicator on the pack aging Check the transport indic...

Page 14: ...mponents Ensure components are stable 3 2 5 Acclimating the power module before installation NOTICE Forming of condensation Damage to the storage system Check the inside of the storage system for condensation before installation Only install the storage system if there is no condensation on the surfaces If the temperature of the packed power module upon delivery is significantly lower than the amb...

Page 15: ...em 2 mounting frame Mounting frame with integrated bracket for securing it to the wall and for compensating for uneven surfaces 3 power module Power module with integrated inverter and switch panel 4 cable entry point Sealed entry point for cables to be routed into the storage system from the back 5 battery screws For securing the battery modules 6 battery modules Storage of electrical power ...

Page 16: ...m power and data cables 4 switch panel Storage system switch panel protected by switch cover with inspection window Overview of switch panel 2 3 4 5 1 No Designation Function 1 Inspection window Cover and protection for control elements on the switch panel 2 Type plate Technical data and other information for identifying the storage system 3 Switch cover Silicone cap that can be removed for operat...

Page 17: ...very to ensure it is complete 1 2 3 KSW 2 4 5 6 2 1 1 1 A 1 3 5 6 8 10 12 4 7 9 1x 1x 2x 5x 4x 2x 1x 11 1x 1x 4x 1x 1x 2 4x 13 E B C D 3 2 14 1x 15 4x 1x 16 A Housing set 1 cover 2 Battery shelves B Mounting frame 1 Mounting frame 2 Feet 3 Supports 4 Spacer plate 5 Floor plate 6 Installation equipment pack ...

Page 18: ... B20 15 Crossbar for mounting frame 16 DRM0 label 11 10 4x 13 1x 12 1x 14 2x 15 1x 16 1x 17 4x 1x 4 3 7x 6x 5 1x 7 1x 6 1x 8 1x 9 2x F A B 1x 1 1x 2 F Extension set optional 1 Housing set 2 Mounting frame 3 BMS communication line grey different lengths 4 Battery cable black 5 Double battery cable 6 Battery shelf 7 Battery coupling 8 Switch cover 9 Dummy plug Ø 20 5 mm 10 Dummy plug Ø 27 8 mm 11 Du...

Page 19: ...e system see Filling out the type plate P 76 4 4 Optional accessories The following optional accessories can be added to the storage system in order to extend its functionality Designation Description Item number Accessories for extending the sonnenBatterie 10 Extension set Second mounting frame incl crossbars with cover For installing up to six additional battery modules see Installing the extens...

Page 20: ...of single conductors adapted to in stallation situation Other required components terminals contact ors relays etc must be acquired as needed for the individual installation situation see Over view of digital inputs and outputs P 55 Residual current device RCD Personal protection Required in networks with TT earthing For specification see section Placing com ponents in the distributor P 35 Miniatu...

Page 21: ... to the mounting frame For securing the earthing strap to the power module For securing the cover Torque spanner AF 10 adjustable to 6 Nm For securing the battery modules Allen key AF 4 For straightening and levelling the mounting frame Torx screwdriver TX 25 If necessary Mount the battery coupling in the extension cabinet Cross slot screwdriver PZ 2 For opening and closing screw type terminals on...

Page 22: ... feet 10 cm from floor 171 cm Table 3 Height of the storage system depends on whether feet are used 5 1 Selecting the installation location NOTICE Insufficient load bearing capacity of wall for mounting Damage to storage system and surrounding area The wall selected for the installation of a storage system must be able to sup port a total weight of 850 kg Ensure that the mounting material and the ...

Page 23: ... of the storage system Sufficient space for installation and maintenance work 5 1 2 Planning cable entry 60 33 Illustration 3 Position for optimal cable entry figure not true to scale all measurements in centimetres sonnen recommends routing the cables for the storage systems out of one opening in the wall dir ectly behind the storage system Alternatively the cables can be routed from above and be...

Page 24: ...ll measure ments in millimetres Minimum diameter of screw head 15 mm Maximum diameter of screw head 30 mm in cluding any tools Screw diameter 8 mm Select washers and wall plugs that suit the screws 5 2 2 Installing the crossbars optional The four crossbars from the scope of delivery can be mounted when the outer openings on the mounting frame are too far to secure the frame to the wall When the cr...

Page 25: ... that the required 10 cm distance from the floor can be achieved Altern atively you can install the feet on the mounting frame in order to mark out the holes and then remove the feet again Mark out the eight holes for the wall bracket When the optional crossbars are moun ted the outer or the inner openings can be used for wall mounting Drill the holes with a suitable diameter for the selected moun...

Page 26: ...he mounting frame is straight and level Tighten the screws with a torque of 6 Nm 5 2 7 Sealing the openings The specified degree of protection for the storage system and therefore touch protection and protection against the ingress of water and foreign bodies is only achieved when all openings on the storage system are sealed as described in the product documentation The openings on the mounting f...

Page 27: ...f the mounting frame using suitable dummy plugs diameter 27 8 mm from the accessories set 5 2 8 Completing the mounting frame The individual components of the housing set must be added to the mounting frame The spacer plate can only be mounted when the battery modules are installed see Posi tioning the battery modules P 43 4 4 2 3 1 5 Mount the floor plate to the mounting frame with three screws a...

Page 28: ...instructions sonnenBatterie 10 Mount the two supports for the cover and the two battery shelves on the mounting frame as shown in the figure Use the screws from the installation equipment pack for this purpose 2 5 Tighten the screws with a torque of 6 Nm ...

Page 29: ...d through the designated cable entry plate 6 3 4 5 1 2 No Type Use 1 Dummy plug Ø 40 Reserve DC module 2 Cable entry point Ø 32 with grommet for two lines Modbus cable Ethernet cable 3 Dummy plug Ø 50 Reserve sonnenProtect 4000 4 Cable entry point Ø 20 5 for one line Signal line for digital input outputs 5 Cable entry point Ø 20 5 for one line AC cable 6 Dummy plug Ø 50 Reserve extension cabinet T...

Page 30: ...er by opening the power mod ule NOTICE Danger due to lifting the power module by the touch guard Damage to the power module Never lift the power module by the touch guard 2 1 3 Lift the power module by bringing the mounting handles on the right and left side of the module into the openings and moving them up 1 Hang the power module in the middle on the top edge of the mounting frame 2 Secure the p...

Page 31: ...lectrical work DANGER Touch voltage in the event of a fault Danger to life due to electrocution Install a selective residual current device with a nominal differential current of 300 mA in TT networks Nominal differential currents of 100 mA or 30 mA are also possible The type of RCD must be selected depending upon the local conditions of the network NOTICE Danger due to touching live components on...

Page 32: ...y There are three different measurement concepts for recording the power The following figures show the consumption measurement standard measurement concept The PV inverter can be single phase or three phase regardless of the building mains The power measurement for production must be installed accordingly Ensure that the maximum permissible unbalanced phase load is observed when using a single ph...

Page 33: ...tional counter 3 CT for consumption L2 12 Public electrical mains 4 CT for consumption L3 13 MCB for PV inverter 5 RCD in TT networks1 14 CT for production L1 6 MCB B20 B25 15 CT for production L2 7 Transformer interface for consumption A2 16 CT for production L3 8 Storage system 17 PV inverter 9 MCB2 18 Transformer interface for production A1 1 Nominal differential current of 300 mA 100 mA or 30 ...

Page 34: ...t connected 12 Public electrical mains 4 CT for consumption L3 not connected 13 MCB for PV inverter 5 RCD in TT networks3 14 CT for production L1 6 MCB B20 B25 15 CT for production L2 not connected 7 Transformer interface for consumption A2 16 CT for production L3 not connected 8 Storage system 17 PV inverter 9 MCB4 18 Transformer interface for production A1 3 Rated differential current of 300 mA ...

Page 35: ... building The power meter is protected using a type B6 miniature circuit breaker 4 An additional miniature circuit breaker can be avoided if there is already an appropriate circuit breaker see Connecting the power meter P 36 A residual current circuit breaker 5 must be installed in networks with TT earthing An RCCB with a rated differential current of 300 mA is sufficient for this RCCBs with a rat...

Page 36: ...s do not have to be installed if the lines are already protected in accordance to the relevant currently applicable regulations and standards 1 A1 input for production 8 CT for production L2 2 A2 input for consumption 9 CT for production L3 3 Terminal strip for voltage measurement 10 Transformer interface for consumption 4 Power meter 11 CT for consumption L1 5 Modbus terminal strip 12 CT for cons...

Page 37: ...cted The other two clamp on cur rent transformers must not be connected 1 2 3 1 2 3 1 2 3 Illustration 10 Connecting the clamp on current transformers for three phase left and single phase right in stallation Do not confuse the phases Power measurement only works if the current and voltage of the same phase are measured Example The clamp on current transformer L1 marked with number 1 must be conne...

Page 38: ...r WM 271 Strommessung Erzeugung Verbrauch Current Measurement Generation Consumption Voltage Metering Spannungsmessung 1 2 3 4 5 6 A1 A2 13 14 15 16 Illustration 12 Removing the front cover Press the clips 2 on both sides of the power meter You might use a small screwdriver Remove the front cover 1 A1 A2 13 14 15 16 Illustration 13 Inserting the touch display Insert the touch display 1 into the po...

Page 39: ...ce until the setting 3P 2 3P ap pears 1 2 3 4 5 6 Illustration 19 SYS screen setting 3P 2 3P Press for a longer period of time until the sign 1 disappears 1 2 3 4 5 6 Illustration 20 SYS screen after changing the measuring mode Press ten times The end screen appears 1 2 3 4 5 6 Illustration 21 End screen Press once The three phase measuring mode is now activated Remove the touch display Insert the...

Page 40: ...n of the Modbus line is earthed in order to ensure optimal data transmission Use a patch cable with the following properties as the Modbus cable The patch cable is Cat 6 The patch cable is shielded Earth the screen of the Modbus line for the power meter6 Connect the patch cable to the central unit of the storage system MOD Meter Use the fixing ties from the accessories set to affix the attached ca...

Page 41: ...ons The storage system establishes a connection to the internet using the Ethernet line The Ethernet line is connected to the building network router and the central unit of the storage system Use a patch cable with the following properties as the Ethernet line The patch cable is Cat 6 The patch cable is shielded Connect the patch cable to the central unit of the storage system ETH Router Use the ...

Page 42: ... storage system Connect the DRED cable to the central unit DRM0 Affixing the sticker A DRM0 sticker is included in the scope of delivery for Australia Affix the DRM0 sticker to the front of the power module The area to the left of the touch guard where there are several stickers already is suitable for this Activating DRM0 in the commissioning assistant The DRM0 function must also be activated in ...

Page 43: ...ositioning two battery modules 1 2 3 Place the two battery modules one in front of the other on the top shelf of the mount ing frame The spacer plate is mounted on the battery modules using two battery screws two washers plastic and one contact disc from the installation equipment pack Use the battery screws to fasten the battery modules to the mounting frame Mount the spacer plate on the battery ...

Page 44: ...f the other on the bottom shelf of the mounting frame Use the battery screws to fasten the battery modules to the mounting frame Place one washer plastic each between the cap nuts for the battery screws and the battery module Tighten the nuts for the battery screws with a torque of 6 Nm The front battery module is battery module 3 and the back module is battery module 4 ...

Page 45: ... that they are not kinked or crushed when the cover is mounted or removed The scope of delivery includes the battery cables BMS communication lines and battery screws for the highest extension level of the storage system If the maximum number of battery modules is not being installed Store the surplus components in the storage system e g on the floor plate These will then be on hand if additional ...

Page 46: ...hem to the mounting frame using cable clips Connect the first BMS communication line to socket BMS First X2 on the central unit Connect the other end to battery module 1 X2 IN Connect the BMS communication line for the last battery module number 2 or 4 to socket BMS Last X1 on the central unit Connect the other end to the battery mod ule X1 OUT Connect the remaining battery modules one after the o...

Page 47: ...n the battery shelves and secure them to the mounting frame using cable clips Connect a battery cable between battery module 1 and socket DC BATT 1 on the central unit Connect a battery cable between battery module 2 and socket DC BATT 2 on the central unit Connect the battery cables for additional battery modules in the same way ...

Page 48: ...ng the battery modules P 12 concerning this Use the commissioning assistant to set the Operating Mode Battery Module Exten sion NOTICE This must take place at least 24 hours before extension as this is the only way the voltage of the installed battery modules can sufficiently adjust to the voltage of the new battery modules to be installed Switching the storage system off to electrically isolate i...

Page 49: ...nting are described in the following sections 7 1 1 Selecting the installation location NOTICE Insufficient load bearing capacity of wall for mounting Damage to storage system and surrounding area The wall selected for the installation of the storage system and extension cab inet must be able to support a weight of 850 kg for each unit Ensure that the mounting material and the wall have the requir...

Page 50: ...Completing the mounting frame P 27 1 3 3 2 Install the battery shelves included in the extension set as shown in the figure Tighten the screws with a torque of 6 Nm 7 1 3 Cable entry point The specified degree of protection for the storage system and therefore touch protection and protection against the ingress of water and foreign bodies is only achieved when all openings on the storage system ar...

Page 51: ...s 2 Dummy plug Ø 40 For sealing 3 Dummy plug Ø 32 For sealing 4 Dummy plug Ø 50 For sealing 5 Dummy plug Ø 20 5 For sealing 6 Dummy plug Ø 20 5 For sealing 7 Cable entry plate Ø 50 Top battery cable four individual cables Bottom 2 BMS communication lines 7 1 4 Mounting the battery coupling 2 1 Mount the battery coupling from the exten sion set to the spacer plate using the four supplied screws ...

Page 52: ...oning the battery modules If just two battery modules are installed in the extension cabinet they must al ways be mounted with the spacer plate on the middle battery shelf 6 5 10 9 8 7 Arrange the battery modules in the extension cabinet as shown in the figure Position and secure the battery modules as de scribed for the storage system see Positioning the battery modules P 43 7 2 2 Connecting the ...

Page 53: ...orage sys tem 7 2 3 Connecting the battery cables DANGER High battery voltage 200 V Danger to life due to electrocution When battery cables are connected the battery coupling always carries the voltage of the battery modules even if the storage system and mains voltage are switched off To disconnect the battery voltage from the battery coupling Unplug the battery cables from all battery modules Th...

Page 54: ...been commissioned for the first time without an ex tension cabinet Invalidate or remove the existing storage capacity notation on the type plate of the storage system Mark the new storage capacity on the type plate Mounting the cover and switch cover Mount the extension cabinet completely similarly to the storage system see Attaching and earthing the cover P 76 and Attaching the switch cover P 77 ...

Page 55: ...uired External components terminals contactors relays etc needed to wire up the digital inputs outputs are not supplied 8 1 Overview of digital inputs and outputs The signal line for using digital inputs and outputs is connected directly to the central unit of the storage system This approach ensures flexible use of the special functions as only the required connections are used and the line lengt...

Page 56: ...I0 21 L Digital input CEI 0 21 local signal 0 25 0 75 5 25 16 DI CEI0 21 T Digital input CEI 0 21 remote shut off 0 25 0 75 5 25 17 N C Reserve 0 25 0 75 18 CEI 0 21 GND CEI 0 21 GND 0 25 0 75 0 50 19 ATS Reserve 0 25 0 75 20 ATS GND Reserve 0 25 0 75 Table 4 Technical data for digital inputs DI and outputs DO PV red 1 PV reduction 1 0 25 0 75 60 SELV 550 PV red 2 PV reduction 2 0 25 0 75 60 SELV ...

Page 57: ...vel 0 As soon as power reduction is required the contacts are activated in levels as shown in the following table If level 1 does not achieve the desired effect for example then level 2 is activated and so forth Relay Level 0 1 2 3 PV red 1 PV red 2 Table 6 Make contact positions depending on activated level Connecting PV reduction Illustration 24 Connecting PV reduction 1 Connecting PV reduction ...

Page 58: ... values for levels 1 and 2 depend on the individual feed in limit of the PV system in question The addition or subtraction of the stated percent values leads to an optimal regu lation by the storage system Example The feed in of the PV system is limited to 50 of the rated power The following values need to be entered in the commissioning assistant Level 1 60 50 plus 10 Level 2 35 50 minus 15 Level...

Page 59: ... the surplus electricity exceeds this limit the digital output remains activated for the duration of the defined Min imal on time in seconds Configuring settings The switching behaviour of the self consumption switch is controlled using the commis sioning assistant Adapt the Threshold to start and Minimal on time for the connected electrical con sumer Application example 1 Heating element K1 Exter...

Page 60: ...combined heat and power station as an electrical generator If a combined heat and power station is used as an electrical generator it must be ensured that it mostly functions as a heat provider i e the highest priority for production is the hot water supply while production of electricity generally takes second priority This means that when digital output CHP of the storage system is activated the...

Page 61: ...rical gen erator must be constant for this as the digital input only detects the statuses of activated or deactivated Configuring settings The power generated by the electrical generator is specified in the commissioning assist ant Activate the combined heat and power station on page Features Specify the constant power of the combined heat and power station Power Application example The type of co...

Page 62: ... 2 5 Recording fluctuating power of an electrical generator The power of an electrical generator that does not produce constant output cannot be recorded via digital input CHP see Recording constant power of an electrical generator P 61 Instead the electrical generator has to be integrated in the power measurement via a separate measurement point To achieve this an additional power meter may be ne...

Page 63: ...Information for the example Storage system without PV connection Measurement concept CP Consumption Measurement Measurement point C measurement point for recording consumption in the building Measurement point P1 measurement point for recording production for the PV system Measurement point P2 measurement point for recording production for the CHP unit The circuits show the connection of the clamp...

Page 64: ...enProtect Adding a sonnenProtect to the storage system allows the system once in stalled to be able to operate both with backup power and in an isolated net work These are functionalities that must be specified when a storage system is registered with a DNO Check whether the storage system data needs to be changed with the DNO or whether the system needs to be re registered 9 1 System components o...

Page 65: ...otect The information on the type plate is required for the safe use of the system and for service matters The following information is specified on the type plate Item designation Item number Technical data of the storage system A duplicate of the type label for the sonnenProtect 4000 must be affixed by the installer to the storage system see Attaching type label to storage system P 73 9 4 Additi...

Page 66: ...em or exten sion cabinet if any Requirements for the installation location Observe the required ambient conditions see Technical data P 89 Observing minimum and maximum distances Install the sonnenProtect at the same level as the top edge of the storage system if possible 5 15 20 Illustration 28 Minimum distances figure not true to scale all measurements in centimetres Observe the minimum distance...

Page 67: ... capacitors can discharge Check that the device is disconnected from the power supply Only licensed electricians are permitted to carry out electrical work DANGER Touch voltage in the event of a fault during backup operation Danger to life due to electrocution A selective residual current device RCD with a nominal differential current of 300 mA must be installed downstream of the sonnenProtect out...

Page 68: ...n implemented and the electrical installation is complete con tinue with section Commissioning the sonnenProtect P 74 9 6 1 Installing the backup circuit s 9 6 1 1 Electrical consumers in backup operation Before installation the installer must explain or clarify with the operator the following points Backup operation does not offer the same output as grid operation Three phase current is not avail...

Page 69: ... within the backup power authorised part must be clearly identified by lettering or graphic symbols At any time observe further local and national requirements and guidelines regarding backup power supply When undertaking electrical work on the distributor in the building the following must be taken into account among other things 1 How is the wiring set up to the desired backup consumers Is indep...

Page 70: ... at the output of the sonnenProtect This RCD protects against electric shock in the backup circuit A residual current device RCD that meets the relevant country specific regulations and is suitable for local grid conditions must be used 9 6 3 Wiring the sonnenProtect Condition ü The backup circuit has been properly installed The information in section Installing the backup circuit s P 68 was obser...

Page 71: ...erview electrical connection in single phase mains 1 Consumers in building 7 Signal line from storage system Protect 2 Consumer in backup circuit 8 Storage system 3 Residual current device RCD 9 Earth connection 4 sonnenProtect 5 Miniature circuit breaker MCB type B 20 A 6 AC line from storage system AC Protect ...

Page 72: ...nProtect signal line Right sonnenProtect AC line 2 Dummy plug Ø 27 8 already mounted from storage system accessories set Earthing cable 10 mm Connecting the earthing cable An earthing conductor with a cross section of 10 mm CU cross section must be in stalled between the storage system and the main earthing terminal Connect the earthing cable to the central unit of the storage system PE 10 mm Conn...

Page 73: ...tage Danger to life due to electrocution To warn electricians Attach the safety label shown below included in scope of delivery to the relevant electrical distributor Illustration 31 Label for attachment to the electrical distributor 9 6 5 Attaching type label to storage system As the sonnenProtect 4000 constitutes an add on to the storage system a duplicate of the type label for the sonnenProtect...

Page 74: ...ing assistant P 79 and activate the sonnenProtect 4000 at the appropriate point The backup buffer can also be set 9 7 1 Setting the backup buffer Proceed as follows to set what percentage of the capacity of the storage system should be available for the sonnenProtect in the event of a grid outage On the web interface of the storage system navigate to the Settings page Change the percentage for bac...

Page 75: ...rotect Switching off the sonnenProtect To switch off the sonnenProtect manually proceed as follows In order to be able to work on the sonnenProtect safely it must be disconnected from the power supply see next sec tion Disconnect the storage system from the power supply see Switching the storage sys tem off to electrically isolate it P 83 Disconnecting the sonnenProtect from the power supply 1 Dis...

Page 76: ... The possible battery capacities with the associated nominal power values can be found in section Technical data P 89 10 2 Attaching and earthing the cover The earth connection between the cover and mounting frame is established via the screw connection The inspection window and sonnen Eclipse have protective film on the inside and out side Remove all protective film before mounting the cover 1 3 ...

Page 77: ...y connected to the screw for securing the power module The screw has been tightened with the correct torque 2 Cable routing All of the cables going into the storage system have been routed through the appropri ate cable entry points All other openings have been sealed with the corresponding dummy plugs 3 Cover mounting The cover is form fitted to the mounting frame The earth connection for the cov...

Page 78: ...sumers in the backup circuit are protected by a corresponding residual current device RCD The electrical cables meet the requirements of all local and national guidelines for cable dimensions The additional earth connection between the storage system and the main earthing ter minal is in place and has a cross section of 10 mm CU cross section or equivalent Table 7 Installation checklist ...

Page 79: ...operation the sonnen Eclipse pulses white The other operating statuses and the associated indications of the sonnen Eclipse are described in section Troubleshooting P 84 11 2 Carrying out first time commissioning First time commissioning must be carried out when the storage system has been installed set up and connected for the first time 11 2 1 Commissioning assistant The storage system is only r...

Page 80: ...which the storage sys tem is also connected 11 2 1 2 Running the commissioning assistant Navigate to the following internet address https find my sonnen batterie com The following window appears 12345 123 456 78 99 Illustration 33 Website find my sonnen batterie com Select the storage system to be configured and click on the Configure Assistent 2 0 button Log in as the Installer Use the initial pa...

Page 81: ... 3 Taking photos to document installation The photo upload is obligatory for both offline commissioning and online com missioning To fully document the installation photos of the finished installation must be taken and send to sonnen 1 Take the described photos of the storage system see Installation photos P 92 2 Go to the following website sonnensupportaustralia com au 3 Navigate to Reference Sys...

Page 82: ...ttery modules P 12 Never continue to operate battery modules which have been deep dis charged 1 Remove the switch cover on the inspection window of the switch panel 2 Press the ON OFF switch The sonnen Eclipse switches off 3 Switch off the grid voltage using the miniature circuit breaker for the mains line 4 Reattach the switch cover to the inspection window Before carrying out any work on the sto...

Page 83: ...witched off To disconnect the battery voltage from the central unit Unplug the battery cables from all battery modules Before working on the storage system it must be completely switched off to be electrically isolated 1 Press the ON OFF switch The sonnen Eclipse switches off 2 Switch off the grid voltage using the miniature circuit breaker for the mains line 3 Take steps to ensure that these swit...

Page 84: ... operation No troubleshooting necessary The sonnen Eclipse of the storage sys tem pulses orange The internet connection to the storage system has been interrupted Check whether the home network router is able to establish an inter net connection If so Ensure that the network cable for the storage system is connected to the home network router The sonnen Eclipse of the storage sys tem illuminates r...

Page 85: ...ep dis charge state and therefore damage the batteries There is nothing that can be done be sides wait until the grid outage is done and the public electricity grid once again begins supplying electrical en ergy The sonnenProtect will then automatically switch to grid operation The storage system is switched off Switch on the storage system Backup operation does not start The Eclipse on the storag...

Page 86: ...ne to the sonnenProtect or a circuit breaker in the backup circuit has switched off The Eclipse on the stor age system pulses green The illumin ated switch on the sonnenProtect does not light up The residual current device RCD or an other circuit breaker in the backup cir cuit has tripped Check the electrical wiring and the connected electrical consumers for faults Switch on the circuit breaker on...

Page 87: ...otect must only be uninstalled by authorised electricians 14 2 Disposal CAUTION Improper transport of battery modules Fire outbreak at battery modules or emission of toxic substances Only transport battery modules in packaging that meets applicable regula tions Never transport damaged battery modules CAUTION Improper disposal of battery modules Explosion or fire outbreak at battery modules or emis...

Page 88: ...tructions sonnenBatterie 10 Illustration 34 WEEE symbol Dispose of the storage system the batteries it contains and the sonnenProtect in an environ mentally friendly way through suitable collec tion systems Contact sonnen GmbH to dispose of old bat teries ...

Page 89: ... 5 5 10 11 10 16 5 10 22 10 27 5 Nominal capacity 5 5 kWh 11 kWh 16 5 kWh 22 kWh 27 5 kWh Usable capacity 5 kWh 10 kWh 15 kWh 20 kWh 25 kWh Charging discharging power12 3 4 kW 4 6 4 8 kW 4 6 4 8 kW 4 6 4 8 kW 4 6 4 8 kW Charging discharging current 14 8 14 2 A 20 A 20 A 20 A 20 A Battery data DC Cell technology lithium iron phosphate LiFePO4 Nominal voltage 102 4 V Working voltage 204 8 V Current ...

Page 90: ... 10 27 5 Dimensions H W D in cm 172 184 69 27 2 x 172 184 69 27 Height without feet in cm 161 Total weight in kg 115 172 268 325 382 Ambient conditions Environment Indoor conditional Operating temperature range14 5 C 45 C Storage temperature range 0 C 40 C Transport temperature range 15 C 50 C Max rel humidity 85 non condensing Permissible installation altitude 2 000 m above sea level Pollution de...

Page 91: ...tch to emergency operation takes place automatic ally through the storage system Switchover time approx 15 seconds Threshold power none starting from 0 W Dimensions weight Dimension H W D in cm 52 23 12 Weight in kg approx 10 Safety protective devices Protection class II Degree of Protection IP65 Overvoltage category 2 Required fault current monitoring Residual current device RCD with a rated diff...

Page 92: ...1 S o nn e n Au s t r a l ia Pt y Lt d 6 0 4 S o u t h T o we r 1 5 Railway Street Chatswood NSW 2067 ACN 611 337 547 0408 802 388 support sonnen com au ...

Page 93: ...2 S o nn e n Au s t r a l ia Pt y Lt d 6 0 4 S o u t h T o we r 1 5 Railway Street Chatswood NSW 2067 ACN 611 337 547 0408 802 388 support sonnen com au ...

Page 94: ...arthing Details on PV system Nominal power kWp Special notes points to be addressed Electrician s declaration I confirm that my details are correct The storage system was installed and commissioned by me in the proper manner I followed the installation instructions in doing so Place date Electrician s signature Operator s declaration I confirm that my details are correct I received the warranty co...

Page 95: ...onse enabling device ESD Electrostatic discharge EVU Energieversorgungsunternehmen de energy supply company GND Ground Grid and system protection Protective measures for ensuring the safety of the grid and systems installed IP International Protection degree of protection us ing to classify systems in terms of their suitable for different ambient environments LED light emitting diode MCB Miniature...

Page 96: ...cuit breaker meets selectivity requirements for upstream and downstream overcurrent protective devices and is used upstream of the electricity meter SOC State of Charge Technical connection conditions The technical connection conditions govern the connection to the electricity grid of the distribution network operators in Germany USB Universal Serial Bus VPN Virtual Private Network ...

Page 97: ......

Page 98: ......

Page 99: ......

Page 100: ...sonnen GmbH Am Riedbach 1 D 87499 Wildpoldsried ...

Reviews: