13-16
Testing and Troubleshooting
Date Code 20011205
SEL-311A Instruction Manual
Figure 13.6: Phase-to-Phase Fault Test Connections Using a Single Current Source
Serial Communication Equipment Connections
A terminal or PC with communications software is necessary to make SEL
OGIC
control equations
setting changes and examine relay event reports. We recommend using a terminal during relay
testing. Figure 13.7 shows typical connections between a computer and the SEL-311A Relay
Port F. Complete details regarding serial communications with the relay may be found in
Section 10: Serial Port Communications and Commands
.
WARNING
!
Use only serial communications cables manufactured by SEL or built
to SEL specifications with the SEL-311A Relay. Damage to the relay
or your communication equipment may result from the use of incorrect
communication connections.
Summary of Contents for SEL-311A
Page 6: ......
Page 8: ......
Page 10: ......
Page 24: ......
Page 40: ......
Page 66: ......
Page 96: ......
Page 98: ......
Page 112: ......
Page 114: ......
Page 122: ......
Page 170: ......
Page 202: ......
Page 204: ......
Page 246: ......
Page 248: ......
Page 286: ......
Page 290: ......
Page 304: ......
Page 306: ......
Page 334: ......
Page 384: ......
Page 386: ......
Page 394: ......
Page 398: ......
Page 402: ......
Page 404: ......
Page 410: ......
Page 412: ......
Page 426: ......
Page 444: ......
Page 460: ......
Page 474: ......