MAINTENANCE
MAINTENANCE SCHEDULE TABLE
4–53
OPENING AND CLOSING CONDENSER
1. Open the rear door on the left side of the machine and
remove bolts (A) (at 2 places) on the right end of the con-
denser.
2. Pull the condenser forward to open it.
3. After cleaning the condenser, close and install it with bolts
(A) (at 2 places).
Tightening torque: 59 - 74 Nm {6.0 - 7.5 kgm}
Summary of Contents for PC210-10 DEMOLITION BASE SPEC.
Page 2: ......
Page 14: ...PRODUCT INFORMATION FOREWORD 1 12...
Page 75: ...OPERATION GENERAL VIEW 3 5...
Page 159: ...OPERATION EXPLANATION OF COMPONENTS 3 89...
Page 251: ...OPERATION MACHINE OPERATIONS AND CONTROLS 3 181...
Page 332: ...MAINTENANCE SCHEDULE TABLE MAINTENANCE 4 22 26 Close engine hood 1...
Page 392: ...END OF SERVICE LIFE MAINTENANCE 4 82...
Page 393: ...SPECIFICATIONS 5 1 SPECIFICATIONS SPECIFICATIONS ALL 0000 001K04A SPECIFICATIONS...
Page 397: ...SPECIFICATIONS SPECIFICATIONS 5 5 PC210 10...
Page 398: ...SPECIFICATIONS SPECIFICATIONS 5 6 PC210LC 10...
Page 444: ...RECOMMENDED ATTACHMENT OPERATIONS ATTACHMENTS AND OPTIONS 6 46...
Page 445: ...REPLACEMENT PARTS 7 1 REPLACEMENT PARTS Replacement parts ALL 0000 001K16A REPLACEMENT PARTS...
Page 453: ...8 1 INDEX...
Page 457: ...COLOPHON 18...