MACHINE OPERATIONS AND CONTROLS
OPERATION
3–206
AFTER DAILY WORK COMPLETION
After daily work completion:ALL-3330-200A00A
1. Walk around the machine and check the work equipment, machine exterior, and undercarriage, also check for
any leakage of oil or coolant. If any problems are found, repair them.
2. Fill the fuel tank.
3. Check the engine compartment for paper and debris. Clean out any paper and debris to avoid a fire hazard.
4. Remove any mud stuck to the undercarriage.
LOCKING
LOCKING:PC220-Q8E0-100K00A
Always lock the following places.
(1) Operator's cab door
Always close the window.
(2) Fuel tank filler port
(3) Engine hood
(4) Tool case cover
(5) Left side door of the machine
(6) Right side door of the machine
(7) Hydraulic tank filler port
(8) Air conditioner FRESH air filter intake port
REMARK
Use the starting switch key to lock and unlock all these places.
Summary of Contents for PC210-10 DEMOLITION BASE SPEC.
Page 2: ......
Page 14: ...PRODUCT INFORMATION FOREWORD 1 12...
Page 75: ...OPERATION GENERAL VIEW 3 5...
Page 159: ...OPERATION EXPLANATION OF COMPONENTS 3 89...
Page 251: ...OPERATION MACHINE OPERATIONS AND CONTROLS 3 181...
Page 332: ...MAINTENANCE SCHEDULE TABLE MAINTENANCE 4 22 26 Close engine hood 1...
Page 392: ...END OF SERVICE LIFE MAINTENANCE 4 82...
Page 393: ...SPECIFICATIONS 5 1 SPECIFICATIONS SPECIFICATIONS ALL 0000 001K04A SPECIFICATIONS...
Page 397: ...SPECIFICATIONS SPECIFICATIONS 5 5 PC210 10...
Page 398: ...SPECIFICATIONS SPECIFICATIONS 5 6 PC210LC 10...
Page 444: ...RECOMMENDED ATTACHMENT OPERATIONS ATTACHMENTS AND OPTIONS 6 46...
Page 445: ...REPLACEMENT PARTS 7 1 REPLACEMENT PARTS Replacement parts ALL 0000 001K16A REPLACEMENT PARTS...
Page 453: ...8 1 INDEX...
Page 457: ...COLOPHON 18...