
RECOMMENDED ATTACHMENT OPERATIONS
ATTACHMENTS AND OPTIONS
6–44
Operations using the swing force
Moving the chisel while carrying out impacting operations
Holding the chisel horizontal or pointed up when carrying out
impacting operations
Twisting the chisel when it penetrates the rock
Pecking operations
Summary of Contents for PC210-10 DEMOLITION BASE SPEC.
Page 2: ......
Page 14: ...PRODUCT INFORMATION FOREWORD 1 12...
Page 75: ...OPERATION GENERAL VIEW 3 5...
Page 159: ...OPERATION EXPLANATION OF COMPONENTS 3 89...
Page 251: ...OPERATION MACHINE OPERATIONS AND CONTROLS 3 181...
Page 332: ...MAINTENANCE SCHEDULE TABLE MAINTENANCE 4 22 26 Close engine hood 1...
Page 392: ...END OF SERVICE LIFE MAINTENANCE 4 82...
Page 393: ...SPECIFICATIONS 5 1 SPECIFICATIONS SPECIFICATIONS ALL 0000 001K04A SPECIFICATIONS...
Page 397: ...SPECIFICATIONS SPECIFICATIONS 5 5 PC210 10...
Page 398: ...SPECIFICATIONS SPECIFICATIONS 5 6 PC210LC 10...
Page 444: ...RECOMMENDED ATTACHMENT OPERATIONS ATTACHMENTS AND OPTIONS 6 46...
Page 445: ...REPLACEMENT PARTS 7 1 REPLACEMENT PARTS Replacement parts ALL 0000 001K16A REPLACEMENT PARTS...
Page 453: ...8 1 INDEX...
Page 457: ...COLOPHON 18...