TRANSPORTATION
OPERATION
3–212
q
Securing the machine when using tie-down point
Tie one end of each chain or wire rope of appropriate strength
to the tie-down holes on the track frame.
X : 50 mm minimum up to 100 mm.
(chain clearance to track)
NOTE: Do not use tie down lugs for towing.
q
Securing the machine when not using tie-down point
Place blocks under both ends of the tracks to prevent the
machine from moving during transportation, and secure the
machine with chains or wire rope of suitable strength. Be par-
ticularly careful to secure the machine in position so it does not
slip to the side.
STOW RADIO ANTENNA
STOW RADIO ANTENNA:PC-K861-822K01A
q
Loosen bolt (2) of radio antenna (1) at the rear of the cab,
turn the antenna to the lower side, then tighten bolt (2)
again to secure radio antenna (1) in position.
q
When unloading the machine from the trailer to operate, fol-
low the reverse procedure to the procedure for stowing to
set radio antenna (1) vertical, then secure it in position with
bolt (2).
Summary of Contents for PC210-10 DEMOLITION BASE SPEC.
Page 2: ......
Page 14: ...PRODUCT INFORMATION FOREWORD 1 12...
Page 75: ...OPERATION GENERAL VIEW 3 5...
Page 159: ...OPERATION EXPLANATION OF COMPONENTS 3 89...
Page 251: ...OPERATION MACHINE OPERATIONS AND CONTROLS 3 181...
Page 332: ...MAINTENANCE SCHEDULE TABLE MAINTENANCE 4 22 26 Close engine hood 1...
Page 392: ...END OF SERVICE LIFE MAINTENANCE 4 82...
Page 393: ...SPECIFICATIONS 5 1 SPECIFICATIONS SPECIFICATIONS ALL 0000 001K04A SPECIFICATIONS...
Page 397: ...SPECIFICATIONS SPECIFICATIONS 5 5 PC210 10...
Page 398: ...SPECIFICATIONS SPECIFICATIONS 5 6 PC210LC 10...
Page 444: ...RECOMMENDED ATTACHMENT OPERATIONS ATTACHMENTS AND OPTIONS 6 46...
Page 445: ...REPLACEMENT PARTS 7 1 REPLACEMENT PARTS Replacement parts ALL 0000 001K16A REPLACEMENT PARTS...
Page 453: ...8 1 INDEX...
Page 457: ...COLOPHON 18...