www.kolidainstrument.com
84
3) Press OK. The coordinate value of the required
point is calculated and displayed.
·
REC: records the coordinate value as a known
point data.
(
Refer to “20. Recording in Record
Mode”
)
·
Press S-O to perform setting-out measurement of
the required point.(Refer to“11. Setting-Out
Measurement”)
OK
Point
Np: 1.885 m
Ep: 0.860 m
Zp: -0.119 m
Dist 0.000m
Ang. 20°45′22″
REC. R.HT OK
S-O
SO. H
S
ZA 89°45′23″
HAR 150°16′54″
dHA -0°00′06″
REC. D/C
<-->
HD
17.3 Setting-out Line (Line)
Setting-out line line measurement is used to measures the horizontal distance and vertical distance
from the required point to the baseline.
The base line should be defined before seting out the straight line.