UPS5000-H-1200 kVA
User Manual (100 kVA Power Modules)
3 Installation
Issue 01 (2020-07-15)
Copyright © Huawei Technologies Co., Ltd.
78
When the EPO switch is in the NO state, ensure that the jumper is connected between EPO_NC and
EPO_12V. When the EPO switch is turned on, EPO is triggered.
3.3 Parallel System Installation
3.3.1 Connecting Power Cables
Procedure
Step 1
Ground each UPS in a parallel system separately, and connect power cables and battery
cables.
Step 2
Choose a parallel mode and connect cables to the parallel system based on site requirements.
Figure 3-37
Conceptual diagram of a 1+1 parallel system
Connect power cables according to port silk screens.