5.1 Powering On and Starting the UPS
Prerequisites
Measure the voltage and frequency values of the UPS upstream input switches. The line
voltage range is 139–485 V AC, and the frequency range is 40–70 Hz.
5.1.1 Powering On the UPS
Context
The following operations are applicable to a single UPS. For parallel systems, contact
Huawei technical support.
Before power-on, ensure that the devices have passed all check items in the section
"Verifying the Installation."
Before power-on, ensure that all the UPS switches and upstream switches are OFF.
Procedure
Step 1
Turn on the SPD switches 1QFS and 2QFS.
Step 2
Turn on the upstream bypass and mains input switches.
After the UPS is powered on, initialization begins. The MDU displays the Huawei logo and
an initialization progress bar.
----End