Prerequisite
l
The NE must be created successfully.
l
You must be an NM user with "NE operator" authority or higher.
Procedure
Step 1
Double-click the unconfigured NE on the Main Topology. Then, the
NE Configuration
Wizard
dialog box is displayed.
Step 2
Select
Manual Configuration
and click
Next
. Then, the
Confirm
dialog box is displayed,
indicating that manual configuration clears the data on the NE.
Step 3
Click
OK
. Then, the
Confirm
dialog box is displayed, indicating that manual configuration
interrupts the service on the NE.
Step 4
Click
OK
. Then, the
Set NE Attribute
dialog box is displayed.
Step 5
Set
NE Name
,
Equipment Type
,
NE Remarks
, and
Shelf Type
and then click
Next
. The NE
slot layout window is displayed.
Step 6
Optional:
Click
Query Logical Information
to query the logical boards of the NE.
Step 7
Optional:
Click
Query Physical Information
to query the physical boards of the NE.
NOTE
The
Query Logical Information
and
Query Physical Information
operations cannot be performed for
a preconfigured NE.
Step 8
Right-click the slot to which you need to add a board. Click
Next
. Then, the
Send
Configuration
window is displayed.
Step 9
Select
Verify and Run
according to the requirements and click
Finish
.
NOTE
Verification is to run the verification command. Click
Finish
to deliver the configuration data to the NE,
thus completing the basic configuration of the NEs. After the successful verification, the NEs start to work
normally.
----End
OptiX OSN 550 Multi-Service CPE Optical Transmission
System
Configuration Guide
2 Creating the Network
Issue 02 (2011-06-30)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
2-7