Manage SUCs and SUDs on the CLI.
Step 2
Establish the connection between SUCs and the PC.
l
Procedure for connecting SUCs to the PC through management network ports is:
1.
Connect one end of the two network cables to each management network port of SUC's
controllers A and B.
2.
Connect the other end of the two network cables to the switch that is connected to the
PC.
l
Procedure for connecting SUCs to the PC through a serial port is:
1.
Connect one end of RJ-45 to the serial port of SUC's controller A or B.
2.
Connect the other end (DB9 end or RJ-45 end) of the serial port to the PC's serial port.
Step 3
Route and bundle cables.
NOTE
For details about how to route and bundle serial cables or management network cables, see
and
13 Basic Cable Routing and Bundling Technology
.
----End
5.21 Connecting Ground Cables
The N8500 must be grounded to prevent damage caused by static electricity or dangers caused
by unexpected creepage.
Prerequisites
The cabinet has been connected to the group pole in the equipment room.
Procedure
Step 1
Connect a ground cable for an SUC.
1.
Use the Phillips screwdriver to loosen the screw on the SUC ground point.
2.
Protrude the screw through the OT of the ground cable and secure the screw to the SUC
ground point.
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
5 N8500 Installation (with the S2600T Storage System as the
Storage Unit)
Issue 02 (2015-09-22)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
78