l
Phillips screwdriver (M3 to M6)
l
Marker pen
l
M6 screws
l
Square-hole positioning pin (matching square holes on channels)
l
Round-hole positioning pins (matching round holes on channels)
Context
CAUTION
Stacking storage devices will damage devices; therefore, storage devices must be placed on
adjustable guide rails.
l
Each SUD is equipped with a pair of adjustable guide rails.
l
Guide rails can be flexibly adjusted from 600 mm to 900 mm, and installed in the cabinet
with a depth from 800 mm to 1200 mm.
l
Adjustable guide rails come preinstalled with square-hole positioning pins. If required,
change square-hole positioning pins to round-hole ones before installing adjustable guide
rails.
NOTE
You can find the round-hole positioning pins in the accessory bag delivered with storage devices.
l
Three M6 screws are used to secure the adjustable guide rails delivered with a 2 U SUD.
shows locations of the three M6 screws.
Figure 6-7
Securing adjustable guide rails
l
Four M6 screws are used to secure the adjustable guide rails delivered with a 4 U SUD.
shows locations of the four M6 screws.
OceanStor N8500 Clustered NAS Storage System
Installation Guide (for T Series V100R005)
6 N8500 Installation (with S5500T Storage System as the
Storage Unit)
Issue 02 (2015-09-22)
Huawei Proprietary and Confidential
Copyright © Huawei Technologies Co., Ltd.
111