Installation
Erection general instructions
L30- 002EN/03
Tightening torques
L31- 001EN/03
Erection general procedures
L31- 003EN/03
Checking for presence of nitrogen (N
2
) in pole parts
L31- 064EN/05
The installation procedure (
advised
), developed
below, imposes a lifting equipment with the following
characteristics :
NOTE
: If it is impossible to obtain the advoca-
ted lifting equipment, one “complementary instal-
lation procedure” is supplied in annexes.
3,000 daN
)
(minimum)
H + 2 m
H
H + 1 m
Support- frame assembly
L31- 139EN/03
Column - chambers coupling
L31- 7142EN/02
Tipping down the pole of the circuit- breaker
and vacuum operation
L31- 722EN/03
Installing terminals with preparation of contact
surfaces
L31- 736EN/03
Installing the capacitors
L31- 742EN/03
Lifting and positionning the pole
L31- 766EN/07
Installing the operating device
L31- 7902EN/02
Continued on next page.
Summary of Contents for GL317D
Page 206: ...Grid Solutions This page is intentionally blank...
Page 212: ...Grid Solutions This page is intentionally blank...
Page 216: ...Grid Solutions This page is intentionally blank...
Page 220: ...Grid Solutions This page is intentionally blank...
Page 295: ...GE Information This page is intentionally blank...
Page 296: ......