Installation
Installation of operating device
GE Information
L31- 7902EN/02
7/12
11- 2016
Coupling the operating device
, continued
Coupling
The table below gives the steps of the operating device coupling :
Step
Action
1
Sling the operating device using a lifting strap (1) like diagram.
NOTE
: Do not remove the roof (17) of the operating device
before slinging.
2
Lift the operating device and make this level.
Approximate weight 300 kg.
3
Approach the operating device in assembly position, the jib of the lift-
ing equipment must be under the stress- shields ring (to avoid that
the cables touch the stress- shields ring).
The final approach must be done with extreme caution.
4
Introduce the operating mechanism shaft (13) into the cylinder (12)
of the pole operating shaft.
5
As soon as the lower fastening screw (9) “
A
” emerge from the hole
of the operating mechanism support (8), install the spacer (26),
washer (10) and the nut (14).
NOTE
: Do not tighten the nut (14).
17
12
13
8
”
A
”
8
1
14
9
10
26
Summary of Contents for GL317D
Page 206: ...Grid Solutions This page is intentionally blank...
Page 212: ...Grid Solutions This page is intentionally blank...
Page 216: ...Grid Solutions This page is intentionally blank...
Page 220: ...Grid Solutions This page is intentionally blank...
Page 295: ...GE Information This page is intentionally blank...
Page 296: ......